Contract No:
HK/2009/05 Wanchai Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing Work
(Stage 1) Environmental
Permit no. EP-356/2009, Further Evironmental permit nos. fep-01/356/2009,
fep-02/356/2009 Monthly Environmental Monitoring
& Audit Report
-
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai,
H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
|
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
9 December |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
EXECUTIVE SUMMARY
1. Introduction
1.1 Scope
of the Report
1.2 Structure
of the Report
2. Project Background
2.1 Background
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3. status of regulatory
compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
4. Monitoring Requirements
4.1 Noise
Monitoring
4.2 Air Monitoring
4.3 Water
Quality Monitoring
5. Monitoring Results
5.1 Noise
Monitoring Results
5.2 Air
Monitoring Results
5.3 Water Monitoring
Results
5.4 Waste
Monitoring Results
6. Compliance Audit
6.1 Noise
Monitoring
6.2 Air
Monitoring
6.3 Water
Quality Monitoring
6.4 Review
of the Reasons for and the Implications of Non-compliance
6.5 Summary
of action taken in the event of and follow-up on non-compliance
7. Cumulative Construction
Impact due to the Concurrent Projects
8. Site Inspection
9. Complaints, Notification of Summons and Prosecution
10. Conclusion
lIST OF
TABLES
Table I Summary of Water Quality Monitoring
Exceedances in Reporting Month
Table 2.1 Schedule 2
Designated Projects under this Project
Table 2.2 Details of
Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/11
Table 3.3 Summary of submission status under FEP-01/356/2009
Condition
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.5 Summary of
submission status under FEP-02/356/2009 Condition
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.7 Summary of
submission status under FEP-03/356/2009 Condition
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.9 Summary of
submission status under EP-356/2009 Condition
Table 4.1 Noise Monitoring Station
Table 4.2 Real Time
Noise Monitoring Station
Table 4.3 Air
Monitoring Station
Table 4.4 Marine Water
Quality Stations for Water Quality Monitoring
Table 4.5 Marine Water
Quality Monitoring Frequency and Parameters
Table 5.1 Noise
Monitoring Stations for Contract no.
HY/2009/11
Table 5.2 Noise
Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Table 5.3 Noise
Monitoring Station for Contract nos. HY/2009/15
Table 5.4 Real Time
Noise Monitoring Station for Contract no. HY/2009/15
Table 5.5 Air Monitoring Stations for Contract no. HY/2009/11
Table 5.6 Air
Monitoring Stations for Contract no. HK/2009/01
Table 5.7 Air
Monitoring Station for Contract no. HK/2009/02
Table 5.8 Air
Monitoring Station for Contract no. HY/2009/15
Table 5.9 Water
Monitoring Stations for Contract no.
HY/2009/11
Table 5.10 Water
Monitoring Stations for Contract no. HK/2009/01
Table 5.11 Water
Monitoring Stations for Contract no. HK/2009/02
Table 5.13 Summary of Water Quality Monitoring Exceedances in
Reporting Month
Table 5.14 Details of
Waste Disposal for Contract no. HY/2009/11
Table 5.15 Details of
Waste Disposal for Contract no. HK/2009/01
Table 5.16 Details of
Waste Disposal for Contract no. HK/2009/02
Table 5.17 Details of
Waste Disposal for Contract no. HY/2009/15
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/11
Table 8.2 Summary of
Environmental Inspections for Contract no. HK/2009/01
Table 8.3 Summary of
Environmental Inspections for Contract no. HK/2009/02
Table 8.4 Summary of
Environmental Inspections for Contract no. HY/2009/15
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Construction
Activities and Recommended Mitigation Measures in Coming Reporting Month
Table I Summary of Water Quality Monitoring Exceedances in
Reporting Month
Table 2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.1 Summary of the current status on licences and/or
permits on environmental protection pertinent to the Project
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/11
Table 3.3 Summary of submission status under FEP-01/356/2009
Condition
Table 3.4 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/01
Table 3.5 Summary of submission
status under FEP-02/356/2009 Condition
Table 3.6 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/02
Table 3.7 Summary of submission status under FEP-03/356/2009
Condition
Table 4.1 Noise Monitoring Station
Table 4.2 Air Monitoring
Station
Table 4.3 Marine Water Quality Stations for Water Quality
Monitoring
Table 4.4 Marine Water Quality Monitoring Frequency and
Parameters
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/11
Table 5.2 Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Table 5.3 Air Monitoring Stations for Contract no. HY/2009/11
Table 5.4 Air Monitoring Stations for Contract no. HK/2009/01
Table 5.5 Air Monitoring Station for Contract no. HK/2009/02
Table 5.6 Water Monitoring
Stations for Contract no. HY/2009/11
Table 5.7 Water Monitoring Stations for Contract no.
HK/2009/01
Table 5.8 Water Monitoring Stations for Contract no.
HK/2009/02
Table 5.9 Summary of Water Quality Monitoring Exceedances in
Reporting Month
Table 5.10 Details of Waste Disposal for Contract no.
HY/2009/11
Table 5.11 Details of Waste Disposal for Contract no.
HK/2009/01
Table 5.12 Details of Waste Disposal for Contract no.
HK/2009/02
Table 8.1 Summary of Environmental Inspections for Contract
no. HY/2009/11
Table 8.2 Summary of Environmental Inspections for Contract
no. HK/2009/01
Table 8.3 Summary of Environmental Inspections for Contract
no. HK/2009/02
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended Mitigation
Measures in Coming Reporting Month
Table 10.2 Summary of Key Construction Activities of Individual
Contract(s) to be commenced in Coming Reporting Month
lIST OF FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project
Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 2.1 Details of the Commencement of Dredging Works for
Contract No. HY/2009/15
Appendix 3.1 Environmental Mitigation Implementation
Schedule
Appendix 4.1 Action
and Limit Level
Appendix
4.2 Copies of Calibration Certificates
Appendix
5.1 Monitoring Schedule for
Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical
Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix
5.4 Water
Quality
Monitoring Results and Graphical Presentations
Appendix
5.5 Real-time Noise Monitoring Results and
Graphical Presentations
Appendix 6.1 Event
Action Plans
Appendix 6.2 Summary for Notification of Exceedance
Appendix
9.1 Complaint Log
Appendix 10.1 Construction
Programme of Individual Contracts
i.
This is the Environmental
Monitoring and Audit (EM&A) Monthly Report – SeptemberNovember August
2010 for the Project of Contract
No. HK/2009/05 –Wanchai Development Phase II and Central Wanchai Bypass - Sampling,
Field Measurement and Testing Work (Stage 1)Wan Chai Development Phase II and Central-Wanchai
Bypass under Environmental Permit no. EP-356/2009 and Further Environmental
permit nos. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009 and FEP-04/356/2009.. This report presents the
environmental monitoring findings and information recorded during the period 28th July August October 2010 to
27th August SeptemberNovember 2010. The cut-off date of
reporting is at 27th of each reporting month.
Construction Activities for the
Reported Period
ii.
During this reporting
period, the major work activities for Contract no. HY/2009/11 included:
·
·
Dredging works;
·
Reclamation works;
·
Construction &
installation of Seawall Block;
·
Floating Out of Caisson
Seawall;
·
Construction &
installation of Seawall Block;
·
Construction of coping;
·
Installation of Caisson
Seawall; and
·
Temporary Protection and
Precautionary Measures to Existing Island Eastern Corridor StructureConstruction of Rock
Mound,
·
Floating Out of Caisson
Seawall,
·
Installation of Caisson
Seawall,
·
Dredging works,
·
Laying of geo-textile,
·
Drainage Works and Seawall
Block Installation
Construction of Rock
Mound,
·
Floating Out of Caisson
Seawall,
·
Installation of Caisson
Seawall,
·
Dredging works,
·
Filling works
·
Laying of geo-textile,
·
Drainage Works and
·
Seawall Block Installation
iii.
During this reporting
period, the major work activities for Contract no. HK/2009/01 included:
·
·
Erection of interim
Engineer’s Principal Office at Works areas WA2 was completed for moving-in on 5
Aug 10.
·
Dredging woks had been
completed about 46% for the open cut trench of cross harbour water mains;
·
Manufacturing of
Taper-lok flange joint;
·
Trial pits for
determination of connection location at both Wan Chai and Tsui Sha Tsui areas;
·
Routine maintenance and
clearance works for silt screens;
·
Trial pits for
determination of connection location at both Wan Chai and Tsim Sha Tsui areas;
·
Due to construction of
SCL works, preparation works for temporary diversion of Convention Plaza
discharge mains;
·
6 pipe piles of P1 Wall
had been installed;
·
Fabrication of conveyor
belt system for filling works at HKCEC water channel reclamation; and
·
Order for 2 jack-up
barges were made for delivery to site in end Nov 10 and mid Jan 11
respectively.
Modification of CATV combine service inspection chamber
is ongoing.
·Installation of staging
piles for trial bored pile was completed and bored pile construction is in
progress.
·Marine site investigation
was completed.
·Dredging works for cross
harbour watermains is on going.
·Dismantling of existing
sloping seawall and removal of armor rock at north-west side of water channel
is stopped and reinstating the rock slope at seawall is in progress.
·Hoarding erection at Tsim
Sha Tsui Salisbury Garden area is completed on 18/08/10. However, only 18m of
artwork panel is installed as design for other location has yet been finalized
from the Engineer.
·Trial pits construction
for determination of pipeline alignment at Convention Avenue is ongoing.
·Fabrication of straight
sections of cross harbour submarine pipes and land water pipes was completed.
·Elbow sections of cross
harbour submarine pipes are being fabricated.
·The assemble of 6 nos. of
tailor made flat top barge was commenced on 14 Aug 10. The fabrication of
dredging crane was completed and will be installed on the tailor make flat top
barge on 21 Aug 10 and ready for dredging by 15 Sept 10 tentatively.
·The registration of 3 mud
barges had been fully licensed. Demonstration to EPD for operation is on going.
Erection of interim Engineer’s Principal Office at
Works areas WA2
·Modification of CATV
combine service inspection chamber
·Installation of staging
piles for trial bored pile was completed and bored pile construction
·Marine site investigation
·Dredging works for cross
harbour watermains
·Dismantling of existing sloping
seawall and removal of armor rock at north-west side of water channel is
stopped and reinstating the rock slope at seawall
·Hoarding erection at Tsim
Sha Tsui Salisbury Garden area
·18m of artwork panel is
installed as design for other location
·Trial pits construction
for determination of pipeline alignment at Convention Avenue
·Fabrication of straight
sections of cross harbour submarine pipes and land water pipes
·Elbow sections of cross
harbour submarine pipes are being fabricated.
·The assemble of 6 nos. of
tailor made flat top barge was commenced on 14 Aug 10. The fabrication of
dredging crane was completed and will be installed on the tailor make flat top
barge on 21 Aug 10 and ready for dredging by 15 Sept 10 tentatively.
iv.
During this reporting period,
the major work activities for Contract no. HK/2009/02 included:
·
Rock filling grade 400 in
Area WCR1 commenced;Site Clearance
·
Hoarding Erection
·
Pre-bored H-piles, ELS
and excavation at WSD Pumping Station
·
Construction of Salt
Water Intake Culvert at Pet Garden
·
Road Modification Works
·
Construction of Cooling
Mains Along Public Road
·
Construction of Temporary
Seawall
·
Dredging for WCR 1
·
Tree Transplanting
·
Equipments Procurement
for TKO 137
·
Dredging in Area WCR1 was
nearly completed;
·
Fabrication of precast cooling
water pumping stations P7, P8, P9, caisson seawalls and seawall blocks was in
progress in the casting yard in the Mainland;
·
Sheet pile installation
for construction of footing for new public toilet and helipad terminal building
commenced;
·
Demolition of covered
walkway at Expo Drive East continued;
·
Bus trial run at the
junction between Harbour Road and Fleming Road by KMB and City Bus for the TTMS
for Trial Pit (TPI) was carried out;
·
Trench excavation for
cooling water mains in southern footpath of Harbour Road near China Resources
Building continued;
·
Pre-boring for ELS of
Salt Water Intake Culvert Bay 9 to 11 commenced;
·
Sheet pile installation
of Salt Water Intake Culvert Bay 20 to 25 at Wan Shing Street continued;
·
Trench excavation for
cooling water main in the footpath of Harbour Centre and Great Eagle Centre,
along Harbour Road and across Harbour Road continued;
·
For cooling water main
construction in Ex-Pet Garden, trench excavation commenced;
·
Pre-bored H-piling for
the Re-provisioned WSD Salt Water Pumping Station continued; and
·
Testing and trial of the
public fill sorting facility at Tseung Kwan O Area 137 continued.
v.
Contract no. HY/2009/15 was commenced on 10 November 2010. The major work activities are included:
·
Installation of 1st Phase Silt Curtain;
·
Maintenance dredging
works at PMA, TCBR2 and TCBR3 for mooring and anchorage rearrangement;
·
Installation of Buoys;
and
·
Demolition of Ex-fireboat Station
·Site Clearance
·Hoarding Erection
·Pre-bored H-piles, ELS and excavation at WSD
Pumping Station
·Construction of Salt
Water Intake Culvert at Pet Garden
·Road Modification Works
·Construction
of Cooling Mains Along Public Road
·Construction of Temporary Seawall
·Dredging for
WCR 1
·Tree
Transplanting
·Equipments
Procurement for TKO 137
Noise Monitoring
vi.
Noise monitoring during
day time and evening time were conducted at the stations M1a, M2b, M3a, M4b and M5b on a weekly basis in the reporting
month. Due to
the excavation and breaking works undertaken next to the monitoring station at M5b - City Garden by the other project during the noise
monitoring, two limit level
exceedances were recorded on 10 and 16 November 2010 at the day time period. Besides, three limit level exceedances were recorded at M1a - Harbour Road Sports
Centre on 4, 10 and 16 November 2010 during the evening time period. Investigation found
that
exceedances were not related to the Project.
Real-time Noise
Monitoring
vii.
Real-time noise
monitoring at FEHD Hong Kong Transport Section
Whitefield Depot and Oil Street Community
Centre have been commenced on 5 October 2010 for
the filling works of Contract no. HY/2009/11. Discontinuous limit level exceedances were recorded at these two stations during the restricted
hour. Investigation
found that exceedances were not related to the Project. Noise monitoring during day
time and evening time were conducted at the City Garden on a weekly basis in
the reporting period. Two limit level exceedances were recorded at M4a on 20
and 27 July 2010 during restricted hours. Investigation found that is not
project related exceedances. Reviewed
the past monitoring results and observation at Station M4a, Victoria Centre
(Station ID: M4b) is proposed as alternative noise monitoring station from
August 2010.
Noise monitoring during daytime was
conducted at the M1a – Harbour
Road Sports Centre in this reporting month. Due to the marine works
undertaken in evening time from 12 July 2010, noise monitoring during evening
time was conducted from 13 July 2010. Three limit level
exceedances were recorded at 3, 10 and 17 during restricted hourin
reporting month. It is concluded as not related to the Project works. However,
baseline noise level at M1 needs to be reviewed in next reporting month.Investigation found that
is not project related exceedances.
Air Quality Monitoring
viii.
Air quality monitoring has been conducted at
stations CMA1ba – Oil Street Community Liaison Centre and CMA2a –
Causeway Bay Community Centre. As no filling works for Contract no. HY/2009/11 was
carriedcommenced
out in mid-reporting
monthAugust
2010, no air quality monitoring
at
stations CMA1b – Oil Street
Community Liaison Centre and
CMA2a – Causeway Bay Community Centre was were undertakencommenced
during on 11
August 2010the reporting month. One No action level exceedance of 1hour TSP was recorded at CMA1b on 24
August 2010. Investigation found that exceedance was not related to the Project.in the reporting month.
Water Quality Monitoring
i.
Water
quality monitoring at 17 19 monitoring
stations werewas conducted three days per week during the
reporting period. The action and limit
level exceedances of water quality monitoring are summarized in Table I.
Investigations were found that the exceedances are not related to the Project
works. The details of the exceedances can be referred to Section 5.3 and 6.3 of
the report.
ix.
Table I Summary of Water Quality Monitoring Exceedances in Reporting
Month
Contract
no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
WSD17 |
0 |
0 |
0 |
1 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C8 |
0 |
0 |
0 |
1 |
2 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
|
C9 |
0 |
0 |
0 |
1 |
2 |
0 |
0 |
0 |
1 |
1 |
1 |
0 |
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
|
WSD20 |
0 |
0 |
0 |
1 |
2 |
1 |
0 |
0 |
1 |
1 |
1 |
1 |
|
WSD7 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C3 |
0 |
0 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
|
C4e |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
2 |
Hy/2009/15 |
C6 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
1 |
4 |
9 |
3 |
0 |
0 |
3 |
4 |
5 |
7 |
Complaints, Notifications of
Summons and Successful Prosecutions
x.
Two complaints were received 8 and 10 November 2010
regarding the visual concerns around the seaside silt screen outside the WSD
freshwater intake pump at Sai Wan Ho and noise nuisance generated from PME at the marine work area
adjacent to Harbour Height. No further complaint was received after
investigation and follow-up action taken.No complaint2Two noiseNo environmental complaints wereas recordedceived on 301 July and 12 August 2010 regarding noise nuisance generated from the dredging works
between 1900 and 0800 in North Point district. Investigation found
that the complaints were considered not valid from the Environmental Permit and Construction Noise Permit
point of view.in the reporting month.
i., notification of summons
and prosecution was recorded in reporting month.
Site Inspections and Audit
xi.
The Environmental Team
(ET) conducted weekly site inspections for Contract nos. HY/2009/11, HK/2009/01 and, HK/2009/02 and HY/2009/15 under EP no. EP-356/2009 in theis
reporting periodmonth. Major observations and recommendations
made during the audit sessions were rectified by the Contractors. No non-conformance
was identified during the site inspections.
xii.
In coming reporting month,
the principal work activities of individual contracts are anticipated as
follows:
Contract no. HY/2009/11- North Point Reclamation
·
Floating Out of Caisson
Seawall,
·
Dredging works;
·
Reclamation works;
·
Construction &
installation of Seawall Block;
·
Floating Out of Caisson
Seawall;
·
Drainage Construction
works;
·
Construction of coping;
and
·
Installation of Caisson
Seawall. Installation
of Caisson Seawall,
·
Dredging works,
·
Construction of Seawall
Block,
·
Works for Fenders and
rubber steps and Drainage works
Floating Out of Caisson Seawall,
·Installation of Caisson Seawall,
·Dredging works,
·Filling works
·Construction of Seawall Block,
·Works for Fenders and rubber steps and
·Drainage works
·
Contract no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai
Bypass at HKCEC
·
·
Installation of pipe pile
wall at West Bridge
·
Installation of pipe
piles of P1 Wall at West Bridge;
·
Removal of the staging
platform & staging piles of trial bored pile;
·
Dredging works and
removal of rock armour for existing sloping seawall at HKCEC water channel;
·
Reclamation works starts
in the HKCEC water channel;
·
Dredging works for cross
harbour watermains;
·
Commencement of removal
of Wan Chai seawall (pipeline connection points);
·
Commencement of temporary
jetty construction;
·
Implementation of TTM
scheme for trial pit at Convention Avenue (Area A2);
·
Implementation of TTM
scheme for pipe laying at Convention Avenue (Area A1-1) for cooling water main
and Harbour Road (Area A5-1) for salt water main and optic fibre;
·
Implementation of TTM
scheme for Stage 1 pipe laying for cooling mains and cross harbour water main
at Expo Drive near HKCEC (Area B1-1, B1-2 & B4-1);
·
Tree transplantation at
Wan Chai and Tsim Sha Tsui (to be completed by early Dec 10);
·
Builder’s work and
structural modification for Sea water pump houses / Transformer room of HKCEC
(to be completed by late Feb 11). The liaison and coordination of interfaces
are ongoing;
·
Preparation work for
E&M first fixing at high level of Pump Station Nos. 1, 3, 4 & 5
(Schedule to be completed by late Mar 2011); and
·
Technical workshop and
coordination meetings with 6 stakeholders.
·Installation of trial bored pile
·Assembly of crane to the custom made dredger
·Dredging works for cross harbour watermains
·Construction of wheel washing facilities
·Commencement of temporary jetty construction
·Implementation of TTM scheme for trial pit at
Convention Avenue (Area A1) and Harbour Road (Area A5)
·Implementation of TTM scheme for Stage 1 pipe
laying for cooling mains and cross harbour water main at Convention Avenue
(Area A1)
·Implementation of TTM scheme for Stage 1 pipe
laying for salt water main and optic fibre at Harbour Road (Area A5)
·Implementation of TTM scheme for Stage 1 pipe
laying for cooling mains and cross harbour water main at Expo Drive near HKCEC
(Area B1)
·Tree transplantation at Wan Chai and Tsim Sha Tsui
·Builder’s work and structural modification for Sea water
pump houses / Transformer room of HKCEC
Installation of pipe pile wall at West Bridge
·Installation of trial
bored pile
·Assembly of crane to the
custom made dredger
·Dredging works for cross
harbour watermains
·Construction of wheel
washing facilities
·Commencement of temporary
jetty construction
·Implementation of TTM
scheme for trial pit at Convention Avenue (Area A1) and Harbour Road (Area A5)
·Implementation of TTM
scheme for Stage 1 pipe laying for cooling mains and cross harbour water main
at Convention Avenue (Area A1)
·Implementation of TTM
scheme for Stage 1 pipe laying for salt water main and optic fibre at Harbour
Road (Area A5)
·Implementation of TTM
scheme for Stage 1 pipe laying for cooling mains and cross harbour water main
at Expo Drive near HKCEC (Area B1)
·Tree transplantation at
Wan Chai and Tsim Sha Tsui
·Builder’s work and structural modification for Sea
water pump houses / Transformer room of HKC
Contract no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan
Chai Bypass at WanChai East
·
Site Clearance
·
Site clearance;
·
Dredging in West
temporary seawall construction in Area WCR1;
·
Rock Filling and
Reclamation in Area WCR1;
·
Casting, delivery and
installation of precast caisson seawalls, pumping stations and seawall blocks;
·
Permanent seawall
construction;
·
Drainage diversion of
existing 1800mm dia. pipe for WCR1 reclamation;
·
Road improvement at
Junction of Fleming Road and Gloucester Road;
·
Road modification at Expo
Drive East;
·
Construction of new
public toilet and helipad terminal building at Expo Drive East;
·
Fabrication and delivery
of HDPE pipe for submarine outfall;
·
Installation of ‘Z’
section of submarine outfall underneath the seawall;
·
Laying of cooling water
mains;
·
Pre-bored H-piling at
proposed WSD Salt Water Pumping Station;
·
Seawall construction near
Expo Drive East;
·
Tree transplanting;
·
Establishing public fill
sorting facility at TKO;
·
Testing with trial run of
public fill sorting facility at TKO;
·
Trench excavation for
construction of Salt Water Intake Culvert at Wan Shing Street;
·
Piling at new Wan Chai
Ferry Pier;
·
Installation of building
services for public toilet; and
·
Construction of precast
units of Box Culvert N1, Salt Water Intake Culvert, Drain FRP-N and Cooling
Water Discharge Pipe in Area WCR1.
·Hoarding Erection
·Pre-bored H-piles, ELS and excavation at WSD
Pumping Station
·Construction of Salt Water Intake Culvert at Pet
Garden
·Road Modification Works
·Construction of Cooling Mains Along Public Road
·Construction of Temporary Seawall
·Dredging for WCR 1
·Tree Transplanting
·Equipments Procurement for TKO 137
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway
Bay Typhoon Shelter Section)
·
·
Maintenance dredging works at TCBR4,
TCBR2 and TCBR3 for mooring and anchorage rearrangement;
·
Place rockfill on the
seabed at TCBR2 and TCBR3;
·
Installation of Buoys;
·
Demolition of Ex-Fireboat
Station; and
·
Erect the CSHK’s Site
Office
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under
Environmental Permit no. EP-356/2009 and Further Environmental
permit nos. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009 and FEP-04/356/2009 for Contractor No.
HK/2009/05 Wan Chai Development Phase II and Central –Wan Chai Bypass –
Sampling, Field Measurement and Testing Work (Stage 1) to
implement the Environmental Monitoring and Audit (EM&A) programme as stipulated
in the EM&A Manual of the approved Environmental Impact Assessment (EIA)
Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register
No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A Manual and “Environmental Monitoring and Audit Requirements” under Particular
Specification Section 27.
1.1.3.
This
report documents the finding of EM&A works for Environmental Permit no. EP-356/2009, Further
Environmental Permit no. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009 and FEP-04/356/2009 during the period
28th July August October to 27th
August
SeptemberNovember 2010. The cut-off
date of reporting is at 27th of each reporting month.
Section 1 Introduction
– details the scope and structure of the report.
Section 2 Project
Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Status of Regulatory Compliance
– summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section 4 Monitoring
Requirements
– summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section 5 Monitoring
Results – summarizes the monitoring results
obtained in the reporting period.
Section 6 Compliance
Audit – summarizes the auditing of
monitoring results, all exceedances environmental parameters.
Section 7 Cumulative Construction Impact due to the
Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section 8 Site Inspection –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a
review of any relevant follow-up actions within the
reporting period.
Section 9 Complaints, Notification of summons and Prosecution
– summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 10 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern
Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on
31 August 2001 and 11 December 2008 respectively.
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested east-west Connaught Road Central/Harcourt Road / Gloucester Road
Corridor (the Corridor) which is currently operating beyond its capacity. The
CWB will provide relief to the existing congestion along the Corridor and cater
for the anticipated growth of traffic on Hong Kong Island. Without the CWB and
its access roads, there will not be sufficient capacity to serve the heavy
traffic demands at both strategic and local levels.
2.2.1.
The
Project is located mainly in Wan Chai North, Causeway Bay and North Point, and
is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick
Pier Street to the west and Tong Shui Road Interchange to the east, as shown in
Figure 2.1.
2.2.2.
The
study area encompasses existing developments along the Wan Chai, Causeway Bay
and North Point shorelines. Major land uses include the Hong Kong Convention
& Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan
Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club
(RHKYC), the Police Officers'’ Club, the Causeway Bay Typhoon Shelter
(CBTS) and commercial and residential developments.
2.2.3.
The
scope of the Project comprises:
·
Land formation for key
transport infrastructure and facilities, including the Trunk Road (i.e.
CWB) and the associated slip roads for connection to the Trunk Road and for through
traffic from Central to Wan Chai and Causeway Bay. The land formed for the above
transport infrastructure will provide opportunities for the development of an
attractive waterfront promenade for the enjoyment of the public
·
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
·
Extension, modification,
reprovisioning or protection of existing storm water drainage outfalls,
sewerage outfalls and watermains affected by the revised land use and land
formation works mentioned above
·
Upgrading of hinterland
storm water drainage system and sewerage system, which would be rendered
insufficient by the land formation works mentioned above
·
Provision of the ground
level roads, flyovers, footbridges, necessary transport facilities and the
associated utility services
·
Construction of the new
waterfront promenade, landscape works and the associated utility services
·
The
Trunk Road (i.e. CWB) within the study area and the associated slip roads for
connection to the Trunk Road.
2.2.4.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (Eps) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these
Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits (FEP) such that the impact monitoring stations are sub-divided
accordingly to facilitate the implementation of EM&A programme and to
streamline the EM&A reporting for individual FEP holders correspondingly.
2.3.2.
In the
reporting month, the dredging works for Contracts no. HK/2009/01 and
HK/2009/02 were commenced on 23 July and 5 July 2010 respectively. The details of individual
contracts are summarized in Table 2.2.
Table 2.2 Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II – Central –Wanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
Pending |
||
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
Pending |
||
HY/2009/11 |
Wan Chai Development Phase II and Central |
DP3 |
17 March 2010 |
HY/2009/15 |
Central-Wanchai
Bypass –
Tunnel (Causeway Bay Typhoon
Shelter Section) |
DP3 |
10 November 2010 |
2.4.1.
Civil
Engineering and Development Department and Highways Department are the overall
project controllers for the Wan Chai Development Phase II and Central-Wan Chai
Bypass respectively. For the construction phase of the Project, Project
Engineer, Contractor(s), Environmental Team and Independent Environmental
Checker are appointed to manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure
2.2. Key personnel and contact
particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principle Resident Engineer |
Mr. Frankie Fan |
|
|
Engineer for CWB |
Principle |
Mr. |
3916 1818 |
3529 2829 |
|
China Harbour- CRBC Joint Venture |
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr.
Daniel Cheung |
3157 1086 |
|||
Environmental Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Paul Yu |
9456 9819 |
2634 1626 |
Operation Manager |
Lau Yee Ching |
9466 3918 |
|||
Construction Manager |
David Wong |
9653 8635 |
|||
Construction Manager |
Wilson Lau |
5183 1270 |
|||
Construction Manager |
Chan Mui Sang |
9864 8615 |
|||
Environmental Officer
(Compliance Manager) |
Brian Wan |
9312 2827 |
|||
Environmental Engineer |
Shelton Chan |
5395 5470 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Eric Lam |
3658-3048 |
|||
Environmental Officer (Compliance Manager) |
Mr. Barry Leung |
3658 3031 |
|||
Environmental Engineer |
Ms. Flora Ng |
3658-3064 |
|||
China State Construction
Engineering (HK) Ltd. |
Contractor
under Contract no. HY/2009/15 |
Project
Manager |
Mr. M Y Wong |
2823 7879 |
2528 5651 |
Site Agent |
Mr. K Y Leung |
9026 8808 |
2566 2192 |
||
|
|
Construction
Manager |
Mr. C K
Kwok |
9779 2162 |
|
|
|
Assistant
Construction Manager (East) |
Mr. Gene
Cheung |
6105 4880 |
|
|
|
Assistant
Construction Manager (West) |
Mr. Tony Chiu |
9090 0606 |
|
|
|
Section
Agent (East) |
Mr. Jason Chan |
9254 1635 |
|
|
|
Section
Agent (West) |
Mr. Tang Ka Tung |
9473 4771 |
|
|
|
Environmental
Manager |
Ms. Anna Yu |
9473 1945 |
|
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For
Contract no. HY/2009/11, the principal work activities in this reporting month
included:
·
Construction of Rock
Mound,
·
Dredging works;
·
Reclamation works;
·
Construction &
installation of Seawall Block;
·
Floating Out of Caisson
Seawall;
·
Construction &
installation of Seawall Block;
·
Construction of coping;
·
Installation of Caisson
Seawall; and
·
Temporary Protection and
Precautionary Measures to Existing Island Eastern Corridor StructureFloating Out of Caisson
Seawall,
·
Installation of Caisson
Seawall,
·
Dredging works,
·
Laying of geo-textile,
·
Drainage Works and Seawall
Block Installation
·Construction of Rock
Mound,
·Floating Out of Caisson
Seawall,
·Installation of Caisson
Seawall,
·Dredging works,
·Filling works;
·Laying of geo-textile,
·Drainage Works and
·Seawall Block
Installation
2.4.4.
For
Contract no. HK/2009/01, the principal work activities in this reporting month
included:
·
·
Erection of interim
Engineer’s Principal Office at Works areas WA2 was completed for moving-in on 5
Aug 10.
·
Dredging woks had been
completed about 46% for the open cut trench of cross harbour water mains;
·
Manufacturing of
Taper-lok flange joint;
·
Trial pits for determination
of connection location at both Wan Chai and Tsui Sha Tsui areas;
·
Routine maintenance and
clearance works for silt screens;
·
Trial pits for
determination of connection location at both Wan Chai and Tsim Sha Tsui areas;
·
Due to construction of
SCL works, preparation works for temporary diversion of Convention Plaza
discharge mains;
·
6 pipe piles of P1 Wall
had been installed;
·
Fabrication of conveyor
belt system for filling works at HKCEC water channel reclamation; and
·
Order for 2 jack-up
barges were made for delivery to site in end Nov 10 and mid Jan 11
respectively.Modification
of CATV combine service inspection chamber is ongoing.
·
Installation of staging
piles for trial bored pile was completed and bored pile construction is in
progress.
·
Marine site investigation
was completed.
·
Dredging works for cross
harbour watermains is on going.
·
Dismantling of existing
sloping seawall and removal of armor rock at north-west side of water channel
is stopped and reinstating the rock slope at seawall is in progress.
·
Hoarding erection at Tsim
Sha Tsui Salisbury Garden area is completed on 18/08/10. However, only 18m of
artwork panel is installed as design for other location has yet been finalized
from the Engineer.
·
Trial pits construction
for determination of pipeline alignment at Convention Avenue is ongoing.
·
Fabrication of straight
sections of cross harbour submarine pipes and land water pipes was completed.
·
Elbow sections of cross
harbour submarine pipes are being fabricated.
·
The assemble of 6 nos. of
tailor made flat top barge was commenced on 14 Aug 10. The fabrication of
dredging crane was completed and will be installed on the tailor make flat top
barge on 21 Aug 10 and ready for dredging by 15 Sept 10 tentatively.
·
The registration of 3 mud
barges had been fully licensed. Demonstration to EPD for operation is on going.
·
Erection of interim
Engineer’s Principal Office at Works areas WA2
·
Modification of CATV
combine service inspection chamber
·
Installation of staging
piles for trial bored pile was completed and bored pile construction
·
Marine site investigation
·
Dredging works for cross
harbour watermains
·
Dismantling of existing
sloping seawall and removal of armor rock at north-west side of water channel
is stopped and reinstating the rock slope at seawall
·
Hoarding erection at Tsim
Sha Tsui Salisbury Garden area
·
18m of artwork panel is
installed as design for other location
·
Trial pits construction
for determination of pipeline alignment at Convention Avenue
·
Fabrication of straight
sections of cross harbour submarine pipes and land water pipes
·
Elbow sections of cross
harbour submarine pipes are being fabricated.
·
The assemble of 6 nos. of
tailor made flat top barge was commenced on 14 Aug 10. The fabrication of
dredging crane was completed and will be installed on the tailor make flat top
barge on 21 Aug 10 and ready for dredging by 15 Sept 10 tentatively.
·
·
2.4.5.
For
Contract no. HK/2009/02, the principal work activities in this reporting month
included:
·
Site Clearance
·
Rock Filling grade 400 in
Area WCR1 commenced;
·
Dredging in Area WCR1 was
nearly completed;
·
Fabrication of precast
cooling water pumping stations P7, P8, P9, caisson seawalls and seawall blocks
was in progress in the casting yard in the Mainland;
·
Sheet pile installation
for construction of footing for new public toilet and helipad terminal building
commenced;
·
Demolition of covered
walkway at Expo Drive East continued;
·
Bus trial run at the
junction between Harbour Road and Fleming Road by KMB and City Bus for the TTMS
for Trial Pit (TPI) was carried out;
·
Trench excavation for
cooling water mains in southern footpath of Harbour Road near China Resources
Building continued;
·
Pre-boring for ELS of
Salt Water Intake Culvert Bay 9 to 11 commenced;
·
Sheet pile installation
of Salt Water Intake Culvert Bay 20 to 25 at Wan Shing Street continued;
·
Trench excavation for
cooling water main in the footpath of Harbour Centre and Great Eagle Centre,
along Harbour Road and across Harbour Road continued;
·
For cooling water main
construction in Ex-Pet Garden, trench excavation commenced;
·
Pre-bored H-piling for
the Re-provisioned WSD Salt Water Pumping Station continued; and
·
Testing and trial of the
public fill sorting facility at Tseung Kwan O Area 137 continued.Hoarding Erection
·
Pre-bored H-piles, ELS
and excavation at WSD Pumping Station
·
Construction of Salt
Water Intake Culvert at Pet Garden
·
Road Modification Works
·
Construction of Cooling
Mains Along Public Road
·
Construction of Temporary
Seawall
·
Dredging for WCR 1
·
Tree Transplanting
·
Equipments Procurement
for TKO 137
·
·
2.4.6.
Contract no. HY/2009/15 was commenced on 10 November 2010. The principal work
activities in
the reporting month are included:
·
Installation of 1st Phase Silt Curtain;
·
Maintenance dredging works at PMA,
TCBR2 and TCBR3 for mooring and anchorage rearrangement; (Dredging operation at PMA for mooring and
anchorage rearrangement is understood to be a non-designated project work
as per EPD memo
(Ref.(2) in EP2/H4/S3/15 Pt.11) replied dated 8 November 2010 on the
proposal of the Private Mooring Area(PMA) dredging with proper implementation of dredging rate, silt
curtains and silt screens deployment and the associated EM&A programme. Details shall be referred to Appendix 2.1)
·
Installation of Buoys;
and
·
Demolition of Ex-Fireboat
Station
2.4.7.
In
coming reporting month, the principal work activities of individual contracts
are anticipated as follows:
Contract
no. HY/2009/11- North Point Reclamation
·
Floating Out of Caisson
Seawall,
·
Dredging works,
·
Reclamation works,
·
Construction &
installation of Seawall Block,
·
Floating Out of Caisson
Seawall,
·
Drainage Construction
works,
·
Construction of coping
and
·
Installation of Caisson
Seawall. Installation
of Caisson Seawall,
·
Dredging works,
·
Construction of Seawall
Block,
·
Works for Fenders and
rubber steps and Drainage works
Floating Out of Caisson
Seawall,
·
Installation of Caisson Seawall,
·
Dredging works,
·
Filling works
·
Construction of Seawall Block,
·
Works for Fenders and rubber steps and
·
Drainage
works
·
Contract
no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at
HKCEC
·
Installation of pipe pile
wall at West Bridge
·
Installation of pipe
piles of P1 Wall at West Bridge;
·
Removal of the staging
platform & staging piles of trial bored pile;
·
Dredging works and
removal of rock armour for existing sloping seawall at HKCEC water channel;
·
Reclamation works starts
in the HKCEC water channel;
·
Dredging works for cross
harbour watermains;
·
Commencement of removal
of Wan Chai seawall (pipeline connection points);
·
Commencement of temporary
jetty construction;
·
Implementation of TTM
scheme for trial pit at Convention Avenue (Area A2);
·
Implementation of TTM
scheme for pipe laying at Convention Avenue (Area A1-1) for cooling water main
and Harbour Road (Area A5-1) for salt water main and optic fibre;
·
Implementation of TTM
scheme for Stage 1 pipe laying for cooling mains and cross harbour water main
at Expo Drive near HKCEC (Area B1-1, B1-2 & B4-1);
·
Tree transplantation at
Wan Chai and Tsim Sha Tsui (to be completed by early Dec 10);
·
Builder’s work and
structural modification for Sea water pump houses / Transformer room of HKCEC
(to be completed by late Feb 11). The liaison and coordination of interfaces
are ongoing;
·
Preparation work for
E&M first fixing at high level of Pump Station Nos. 1, 3, 4 & 5
(Schedule to be completed by late Mar 2011); and
·
Technical workshop and
coordination meetings with 6 stakeholders.
·Installation of trial bored pile
·Assembly of crane to the custom made dredger
·Dredging works for cross harbour watermains
·Construction of wheel washing facilities
·Commencement of temporary jetty construction
·Implementation of TTM scheme for trial pit at
Convention Avenue (Area A1) and Harbour Road (Area A5)
·Implementation of TTM scheme for Stage 1 pipe
laying for cooling mains and cross harbour water main at Convention Avenue
(Area A1)
·Implementation of TTM scheme for Stage 1 pipe
laying for salt water main and optic fibre at Harbour Road (Area A5)
·Implementation of TTM scheme for Stage 1 pipe
laying for cooling mains and cross harbour water main at Expo Drive near HKCEC
(Area B1)
·Tree transplantation at Wan Chai and Tsim Sha Tsui
·Builder’s work and structural modification for Sea water
pump houses / Transformer room of HKCEC
·Installation of pipe pile
wall at West Bridge
·Installation of trial
bored pile
·Assembly of crane to the
custom made dredger
·Dredging works for cross
harbour watermains
·Construction of wheel
washing facilities
·Commencement of temporary
jetty construction
·Implementation of TTM
scheme for trial pit at Convention Avenue (Area A1) and Harbour Road (Area A5)
·Implementation of TTM
scheme for Stage 1 pipe laying for cooling mains and cross harbour water main
at Convention Avenue (Area A1)
·Implementation of TTM
scheme for Stage 1 pipe laying for salt water main and optic fibre at Harbour
Road (Area A5)
·Implementation of TTM scheme
for Stage 1 pipe laying for cooling mains and cross harbour water main at Expo
Drive near HKCEC (Area B1)
·Tree transplantation at
Wan Chai and Tsim Sha Tsui
·Builder’s work and
structural modification for Sea water pump houses / Transformer room of HKCEC
·
·
·
Contract
no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at
WanChai East
·
Site Clearance
·
Site clearance;
·
Dredging in West
temporary seawall construction in Area WCR1;
·
Rock Filling and
Reclamation in Area WCR1;
·
Casting, delivery and
installation of precast caisson seawalls, pumping stations and seawall blocks;
·
Permanent seawall
construction;
·
Drainage diversion of
existing 1800mm dia. pipe for WCR1 reclamation;
·
Road improvement at
Junction of Fleming Road and Gloucester Road;
·
Road modification at Expo
Drive East;
·
Construction of new
public toilet and helipad terminal building at Expo Drive East;
·
Fabrication and delivery
of HDPE pipe for submarine outfall;
·
Installation of ‘Z’
section of submarine outfall underneath the seawall;
·
Laying of cooling water
mains;
·
Pre-bored H-piling at
proposed WSD Salt Water Pumping Station;
·
Seawall construction near
Expo Drive East;
·
Tree transplanting;
·
Establishing public fill
sorting facility at TKO;
·
Testing with trial run of
public fill sorting facility at TKO;
·
Trench excavation for
construction of Salt Water Intake Culvert at Wan Shing Street;
·
Piling at new Wan Chai
Ferry Pier;
·
Installation of building
services for public toilet; and
·
Construction of precast
units of Box Culvert N1, Salt Water Intake Culvert, Drain FRP-N and Cooling
Water Discharge Pipe in Area WCR1.Hoarding Erection
·
Pre-bored H-piles, ELS
and excavation at WSD Pumping Station
·
Construction of Salt
Water Intake Culvert at Pet Garden
·
Road Modification Works
·
Construction of Cooling
Mains Along Public Road
·
Construction of Temporary
Seawall
·
Dredging for WCR 1
·
Tree Transplanting
·
Equipments Procurement
for TKO 137
Contract no. HY/2009/15 - Central-Wanchai Bypass
– Tunnel (Causeway Bay Typhoon Shelter Section)
·
Maintenance dredging works at TCBR4,
TCBR2 and TCBR3 for mooring and anchorage rearrangement;
·
Place rockfill on the
seabed at TCBR2 and TCBR3;
·
Installation of Buoys;
·
Demolition of Ex-Fireboat
Station; and
·
Erect the CSHK’s Site
Office
·
3.1.1.
A
summary of the current status on licences and/or permits on environmental
protection pertinent to the Project is shown in Table 3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009/A |
4 Aug |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
|
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb
2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental
Permit |
FEP-04/356/2009 |
22 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/364/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further
Environmental Permit |
FEP-03/364/2009 |
12 Jul |
Valid |
Further Environmental
Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Valid |
Further Environmental
Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
3.1.2.
Due
to the multi-contract nature of the Project, the status of permits and/or
licences under the individual contract(s) are presented as below:
Contract no. HY/2009/11 – Central – Wanchai
Bypass, North Point Reclamation
3.1.3.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and submission under FEP-01/356/2009 for contract no. HY/2009/11 are
shown in Table 3.2 and Table 3.3.
Table 3.2 Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/11
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
N/A |
Valid |
Notification of Works Under APCO |
314911 |
9 Mar 2010 |
N/A |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0371-10 |
7 May 2010 |
10 May 2010 to 31 Oct 2010 |
Expired |
GW-RS0534-10 |
22 Jun 2010 |
29 Jun 2010 to 28 Dec 2010 |
Valid |
|
GW-RS0870-10 |
6 Oct 2010 |
1 Nov 2010 to 30 Apr 2011 |
Valid |
|
Registration as a Chemical Waste Producer |
WPN:
5213-151-C3631-02 |
12 Oct 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7010037 |
13 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00007942-2010 |
29 Nov 2010 |
30 Nov 2015 |
Valid |
Dumping Permit (Type 1 – Open
Sea Disposal) |
EP/MD/10-055 |
26 Aug 2010 |
10 Sep 2010 to 30 Dec 2010 |
Valid |
Dumping Permit (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) |
EP/MD/11-073 |
7 Oct 2010 |
10 Oct 2010 to 9 Nov
2010 |
Expired |
EP/MD/11-087 |
25 Nov 2010 |
10 Nov to 9 Dec 2010 |
Valid |
Table 3.3 Summary
of submission status under FEP-01/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
18 Dec 2009 |
Condition 2.7 |
Submission of works schedule and location plan |
8 Feb 2010 |
Condition
2.8 |
Silt
Curtain Deployment Plan |
25 Feb 2010 |
|
Revised Silt Curtain
Deployment Plan (Rev. 3) |
4 Dec 2010 |
Condition
2.9 |
Silt
Screen Deployment Plan |
25 Feb 2010 |
|
Revised Silt Screen
Deployment Plan |
10 May 2010 |
|
Silt Screen Deployment
Plan (Rev. 4) |
1 Nov 2010 |
Condition
2.10 |
Coral
Translocation Plan |
20 Nov 2009 |
Condition
2.16 |
Noise
Management Plan |
1 Mar 2010 |
|
Revised Noise
Management Plan |
28 Sep 2010 |
Condition
2.17 |
Landscape
Plan |
12
May 2010 |
|
Revised landscape Plan |
30 Jun 2010 |
|
Submission of
Supplementary Information - Revised Management & Maintenance Schedule for
Submitted Revised Landscape Plan |
25 Aug 2010 |
Contract
no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at
HKCEC
3.1.4.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and submission under FEP-02/356/2009 for contract no.
HK/2009/01 under
FEP-02/356/2009 are shown in Table 3.4 and Table 3.5.
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0763-10 |
1 Sep 2010 |
14 Sep 2010
to 14 Mar 2011 |
Valid |
|
GW-RS0771-10 |
1 Sep 2010 |
1 Sep 2010
to 28 Feb 2011 |
Valid |
|
GW-RS0772-10 |
3 Sep 2010 |
15 Sep 2010
to 14 Mar 2011 |
Valid |
|
GW-RS0819-10 |
15 Sep 2010 |
16 Sep 2010
to 15 Mar 2011 |
Valid |
|
GW-RS0900-10 |
20 Oct 2010 |
27 Oct 2010
to 26 Mar 2011 |
Valid |
|
GW-RS0965-10 |
8 Nov 2010 |
22 Nov 2010
to 21 May 2011 |
Valid |
|
GW-RS1034-10 |
26 Nov 2010 |
27 Nov 2010
to 26 May 2011 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar |
Valid |
|
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1 – Open
Sea Disposal) |
EP/MD/10-060 |
30 Apr 2010 |
4 May to 3 Nov 2010 |
|
|
EP/MD/11-083 |
23 Nov 2010 |
24 Nov 2010 to 23 May 2011 |
Valid |
Dumping Permit (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) |
EP/MD/11-071 |
22 Sep 2010 |
1 to 31 Oct 2010 |
Expired |
EP/MD/11-082 |
5 Nov 2010 |
8 Nov to 7 Dec 2010 |
Valid |
Table 3.5 Summary
of submission status under FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and Location
Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
19 Apr 2010 |
Condition 2.9 |
Silt Screen Deployment Plan |
19 Apr 2010 |
Conditions 2.8 and 2.9 |
Supplementary Document on Silt Curtain and Silt
Screen Deployment Plan |
19 Jul 2010 |
Report on Field Testing for Silt Curtain |
26 Aug 2010 |
|
Report on Field Testing for Silt Curtain (Rev. A) |
15 Nov 2010 |
|
Condition 2.17 |
Noise Management Plan |
23 Apr 2010 |
Condition 2.18 |
Landscape Plan (Erection of
Decorative Screen Hoarding along Construction Site around Hong Kong
Exhibition and Convention Centre) |
15 May 2010 |
Landscape Plan (Night-time Lighting) |
22 Oct 2010 |
|
|
Landscape Plan (Rev. B) |
15 Nov 2010 |
Contract
no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at
WanChai East
3.1.5.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and submission under FEP-03/356/2009 for contract no.
HK/2009/02 under
FEP-03/356/2009 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313962 |
2 Feb
2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
piling equipment |
PP-RS0016-10 |
14 Apr 2010 |
1 Jun
2010 to 31 |
Valid |
PP-RS0037-10 |
3 Nov 2010 |
1 Dec 2010 to 31 May 2011 |
Valid |
|
PP-RS0041-10 |
26 Nov 2010 |
1 Dec 2010 to 28 Feb 2011 |
Valid |
|
Construction Noise Permit (CNP) for
non-piling equipment
|
GW-RS0653-10 |
30 July 2010 |
1 Aug 2010 to 31 Jan
2011 |
Valid |
GW-RS0777-10 |
13 Sept 2010 |
01 Oct 2010 to 31 Mar
2011 |
Valid |
|
GW-RS0817-10 |
17 Sept 2010 |
17 Sep 2010 to 16 Nov
2010 |
Expired |
|
GW-RS0891-10 |
14 Oct 2010 |
09 Nov 2010 to 12 Jan
2011 |
Valid |
|
GW-RS0910-10 |
22 Oct 2010 |
25 Oct 2010 to 24 Apr 2011 |
Valid |
|
GW-RS0934-10 |
22 Oct 2010 |
25 Oct 2010 to 24 Apr 2011 |
Valid |
|
|
GW-RS0958-10 |
3 Nov 2010 |
16 Nov 2010 to 16 Jan 2011 |
Valid |
|
GW-RS0961-10 |
5 Nov 2010 |
6 Nov 2010 to 5 May 2011 |
Valid |
|
GW-RS0993-10 |
10 Nov 2010 |
24 Nov 2010 to 31 Jan 2011 |
Valid |
|
GW-RS1011-10 |
15 Nov 2010 |
18 Nov 2010 to 17 May 2011 |
Valid |
|
GW-RS1023-10 |
25 Nov 2010 |
1 Dec 2010 to 30 Apr 2011 |
Valid |
|
GW-RS1033-10 |
22 Nov 2010 |
23 Nov 2010 to 21 May 2011 |
Valid |
Discharge
Licence |
WT00006249-2010 |
22 Mar
2010 |
31 Mar
2015 |
Valid |
WT00006436-2010 |
15 Apr
2010 |
30 Apr
2015 |
Valid |
|
WT00006673-2010 |
14 May
2010 |
31 Mar
2015 |
Valid |
|
WT00006757-2010 |
28 May
2010 |
31 May
2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
|
Valid |
|
Billing
Account under Waste Disposal Ordinance |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
|
Dumping
Permit (Type 1 – Open Sea Disposal) |
EP/MD/10-069 |
6 May
2010 |
6 May to
5 Nov 2010 |
|
|
EP/MD/10-093 |
25 Nov 2010 |
29 Nov 2010 to 28 May 2011 |
Valid |
Dumping
Permit (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined
Marine disposal) |
EP/MD/11-072 |
22 Sep 2010 |
6 Oct 2010 to 5 Nov 2010
|
Expired |
EP/MD/11-090 |
9 Nov 2010 |
10 Nov 2010 to 9 Dec 2010 |
Valid |
Table 3.7 Summary
of submission status under FEP-03/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
|
Commencement Date of Construction of Marine Works |
8 April 2010 |
Condition 2.6 |
Management Organization of Main Construction
Companies |
10 April 2010 |
Condition 2.7 |
Works Schedule and Location Plans |
8 April 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan Rev. A |
20 April 2010 |
|
Silt Curtain Deployment Plan Rev. B |
25 May 2010 |
|
Silt Curtain Deployment Plan Rev. C |
14 Jun 2010 |
Condition 2.9 |
Silt Screen Deployment Plan |
21 April 2010 |
|
Supplementary Information for Existing WSD Salt
Water Intakes at Quarry Bay and Sai Wan Ho |
5 Oct 2010 |
Condition 2.17 |
Noise Management Plan |
6 May 2010 |
Condition 2.18 |
Landscape Plan (Decorative Screen Hoarding) |
11 May 2010 |
|
Landscape Plan (Control of Night Time
Lighting) |
2 June 2010 |
Contract no. HY/2009/15 - Central-Wanchai Bypass
– Tunnel (Causeway Bay Typhoon Shelter Section)
3.1.6.
Summary of the current
status on licences and/or permits on environmental protection pertinent and
submission for contract no. HY/2009/15 under EP-356/2009 are shown in Table
3.8 and Table 3.9.
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or
Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further
Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0997-10 |
11 Nov 2010 |
15 Nov 2010 to 14 May 2011 |
Valid |
Registration as a
Chemical Waste Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance |
7011553 |
30 Sep 2010 |
27
Sep 2010 to 27 Jan 2016 |
Valid |
Dumping
Permit (Type 1 – Open Sea Disposal) |
EP/MD/11-080 |
06 Oct 2010 |
04 Nov 2010 to 03 May 2011 |
Withdrawal on 1 Dec 2010 |
|
EP/MD/11-097 |
29 Nov 2010 |
1 Dec 2010 to 31 May 2011 |
Valid |
Dumping
Permit (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined
Marine disposal) |
EP/MD/11-081 |
06 Oct 2010 |
01 Nov 2010 to 30 Nov 2010 |
Valid |
EP/MD/11-094 |
24 Nov 2010 |
1 Dec 2010 to 31 Dec 2010 |
Valid |
Table 3.9 Summary of
submission status under EP-356/2009 Condition
EP
Condition |
Submission |
Date of
Submission |
Condition
2.7 |
Works Schedule and Location Plans |
27 Oct 2010 |
|
Amendment for Works Schedule and Location Plans |
12 Nov 2010 |
Condition
2.8 |
Silt Curtain Deployment Plan |
27 Oct 2010 |
|
Amendment for Silt Curtain Deployment Plan |
12 Nov 2010 |
Condition
2.9 |
Silt Screen
Deployment Plan |
27 Oct 2010 |
Condition 2.23 |
Noise Management
Plan |
27 Oct 2010 |
|
Amendment
for Noise Management Plan |
12 Nov 2010 |
3.1.7.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 3.1.
Noise Monitoring Stations
4.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table
4.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour
Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
|
|
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta
Secondary School |
Real-time Noise Monitoring
Stations
4.1.2.
The real-time noise monitoring
stations for the Project are listed and shown in Table 4.2 and Figure 4.1.. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table
4.2 Real Time Noise Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield
Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
4.1.1.Reviewed the past
monitoring results and observation at Station M4a, the monitoring location at
Causeway Bay Community Centre is facing and closed to the Island Eastern
Corridor. Traffic noise is the major noise source obtained in the monitoring
that cannot be reflected the
fact of the construction noise from the construction site.
Victoria Centre (Station ID: M4b) is proposed as alternative noise monitoring station,
which is more appropriate and
representative as noise monitoring station for monitoring the construction
noise arising from the near construction site.
Noise Monitoring Parameters, Frequency
and Duration
4.1.3. The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.
4.1.4. Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:
·
one set of measurements between 0700 and 1900
hours on normal weekdays.
4.1.5. If construction works are extended to include works during the hours of 1900 – 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
4.1.6. As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.
4.1.7. Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.
4.1.8. The sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency before deployment to the site and during each site visit. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring Stations
4.2.1.
The air monitoring stations for the
Project are listed and shown in Table 4.2 3 and Figure 4.1.
Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.23 Air
Monitoring Station
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North
Point |
CMA2a |
Causeway Bay Community Centre |
Causeway
Bay |
CMA3a |
Future CWB site office at Wanchai
Waterfront Promenade |
Causeway
Bay |
CMA4a |
Society for the Prevention of
Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds opposite to
Pedestrian Plaza |
Wan Chai |
CMA6a |
Future AECOM site office at Work
Area |
Wan Chai |
Air Monitoring Parameters, Frequency and
Duration
4.2.2. One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
4.2.3. All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.
4.2.4. For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring
Equipment
4.2.5. High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6 - 1.7 m3 per minute adjustable flow
range;
·
equipped with a timing / control device with
+/- 5 minutes accuracy for 24 hours operation;
·
installed with elapsed-time meter with +/- 2
minutes accuracy for 24 hours operation;
·
capable of providing a minimum exposed area
of 406 cm2;
·
flow control accuracy: +/- 2.5% deviation
over 24-hour sampling period;
·
equipped with a shelter to protect the filter
and sampler;
·
incorporated with an electronic mass flow rate
controller or other equivalent devices;
·
equipped with a flow recorder for continuous
monitoring;
·
provided with a peaked roof inlet;
·
incorporated with a manometer;
·
able to hold and seal the filter paper to the
sampler housing at horizontal position;
·
easily changeable filter; and
·
capable of operating continuously for a
24-hour period.
4.2.6. Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7. A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.
4.2.8.
Filter paper of size 8" x
10" shall be labeledlabelled before sampling. It shall be a clean
filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
4.2.9. After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.
4.2.10. All the collected samples shall be kept in a good condition for 6 months before disposal.
4.3.1. The EIA Report has identified that the key water quality impact would be associated with the dredging works during the construction phase. Marine water quality monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is therefore recommended to be carried out at selected WSD flushing water intakes. The impact monitoring should be carried out during the proposed dredging works to ensure the compliance with the water quality standards.
Water Quality Monitoring Stations
4.3.2.
It is proposed to monitor the water
quality at 9 WSD salt water intakes and 12 cooling water intakes along the
seafront of the Victoria Harbour. The proposed water quality monitoring
stations of the Project are shown in Table 4.3 4 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table
4.3
4 Marine
Water Quality Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt
Water Intake |
|||
WSD7 |
Kowloon South |
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
Kennedy Town |
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW1 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling
Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Wan Chai Tower and Great Eagle
Centre (Eastern) |
835932.8 |
815888.2 |
C4w |
Wan Chai Tower and Great Eagle
Centre (Western) |
835629.8 |
815889.2 |
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
C6 |
|
837009.6 |
815999.3 |
C7 |
Windsor House |
837193.7 |
816150.0 |
C8 |
City Garden |
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed
HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung
Kai Centre (Reprovision) |
836291.4 |
816029.7 |
RC7 |
Windsor House (Temporary Dilution) |
837245.2 |
816156.6 |
Water Quality Parameters
4.3.3. Monitoring of dissolved oxygen (DO), turbidity and suspended solids (SS) shall be carried out at WSD flushing water intakes and cooling water intakes. DO and Turbidity are measured in-situ while SS is determined in laboratory.
4.3.4. In association with the water quality parameters, other relevant data shall also be measured, such as monitoring location/position, time, sampling depth, water temperature, pH, salinity, dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal stage, and any special phenomena and work underway at the construction site etc.
Sampling Procedures and Monitoring
Equipment
4.3.5.
The interval between two sets of
monitoring should not be less than 36 hours except where there are exceedances
of Action and/or Limit Levels, in which case the monitoring frequency will be
increased. Table 4.4 5 shows the proposed
monitoring frequency and water quality parameters. Duplicate in-situ measurements and water sampling should be
carried out in each sampling event. For
selection of tides for in-situ measurement and water sampling, tidal range of
individual flood and ebb tides should be not less than 0.5m.
Table
4.45 Marine
Water Quality Monitoring Frequency and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week baseline
monitoring period |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine
construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
After
completion of marine construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1. For
selection of tides for in-situ measurement and water sampling, tidal range of
individual flood and ebb tides should be not less than 0.5m.
2. Turbidity
should be measured in situ whereas SS should be determined by laboratory.
Dissolved Oxygen and Temperature
Measuring Equipment
4.3.6. The instrument should be a portable, weatherproof dissolved oxygen measuring instrument complete with cable, sensor, comprehensive operation manuals, and use a DC power source. It should be capable of measuring:
·
a dissolved oxygen level in the range of 0-20
mg/l and 0-200% saturation
·
a temperature of 0-45 degree Celsius
4.3.7. It should have a membrane electrode with automatic temperature compensation complete with a cable. Sufficient stocks of spare electrodes and cables should be available for replacement where necessary. (e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).
4.3.8. Should salinity compensation not be build-in in the DO equipment, in-situ salinity shall be measured to calibrate the DO equipment prior to each DO measurement.
Turbidity Measurement Instrument
4.3.9. The instrument should be a portable, weatherproof turbidity-measuring instrument complete with comprehensive operation manual. The equipment should use a DC power source. It should have a photoelectric sensor capable of measuring turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model 2100P or an approved similar instrument).
Sampler
4.3.10. A water sampler comprises a transparent PVC cylinder, with a capacity of not less than 2 litres, and can be effectively sealed with latex cups at both ends. The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (e.g. Kahlsico Water Sampler or an approved similar instrument).
Sample Container and Storage
4.3.11. Water samples for suspended solids measurement should be collected in high-density polythene bottles, packed in ice (cooled to 4°C without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection for analysis.
Water Depth Detector
4.3.12. A portable, battery-operated echo sounder shall be used for the determination of water depth at each designated monitoring station. This unit can either be handheld or affixed to the bottom of the workboat, if the same vessel is to be used throughout the monitoring programme.
Salinity
4.3.13. A portable salinometer capable of measuring salinity in the range of 0-40 ppt shall be provided for measuring salinity of the water at each of monitoring location.
Monitoring Position Equipment
4.3.14. A hand-held or boat-fixed type digital Global Positioning System
(GPS) with way pointwaypoint bearing indication or other
equivalent instrument of similar accuracy shall be provided and used during
monitoring to ensure the monitoring vessel is at the correct location before
taking measurements.
Calibration of In-situ Instruments
4.3.15. All in-situ monitoring instrument shall be checked, calibrated and certified by a laboratory accredited under HOKLAS or equivalent before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring. Responses of sensors and electrodes should be checked with certified standard solutions before each use. Wet bulb calibration for a DO meter shall be carried out before measurement at each monitoring location.
4.3.16. For the on site calibration of field equipment by the ET, the BS 127:1993, "Guide to Field and on-site test methods for the analysis of waters" should be observed.
4.3.17. Sufficient stocks of spare parts should be maintained for replacements when necessary. Backup monitoring equipment shall also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.
4.3.18. Current calibration certificates of equipments are presented in Appendix 4.2.
Laboratory Measurement / Analysis
4.3.19. Analysis of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the monitoring stations for carrying out the laboratory SS determination. The SS determination work shall start within 24 hours after collection of the water samples. The SS determination shall follow APHA 19ed or equivalent methods subject to the approval of IEC and EPD.
5.0.1. The environmental monitoring will be implemented based on the division of works areas of each designed project managed under different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1. The monitoring results are presented in according to the Individual Contract(s).
5.0.2. In the reporting month, the concurrent contracts are as follows:
Contract no. HY/2009/11 Central - Wan Chai Bypass - North Point Reclamation;
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central-Wan Chai Bypass at Hong Kong Convention and Exhibition Centre; and
Contract no. HK/2009/02 Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan Chai East
Contract no. HY/2009/15 - Central-Wanchai
Bypass –
Tunnel (Causeway Bay Typhoon
Shelter Section)
5.0.3. The environment monitoring schedules for reporting month and coming month are presented in Appendix 5.1.
Contract
no. HY/2009/11 – Central – Wanchai Bypass, North Point Reclamation
5.1.1. The proposed division of noise monitoring stations for Contract no. HY/2009/11 are summarized in Table 5.1 below:
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/11
Station |
Description |
M4b |
|
M5b |
City Garden |
5.1.2.
Day time and evening period noise
monitoring was conducted at the City Garden and Causeway Bay CommunityVictoria Centre in
the reporting month.
5.1.3.
Noise monitoring results
measured in this reporting period are reviewed and summarized. Two action levelNo Due to the
excavation and breaking works undertaken next to the monitoring station at M5b
- City Garden by the other project during the noise monitoring, two limit level
exceedances were recorded on 10 and 16 November 2010 at the day time period.due to
the receipt of noise complaints
dated 31 July and 12
August 2010 regarding the noise
nuisance generated from the dredging works at North Pointin the reporting month Details of noise
monitoring results and graphical presentation can be referred in Appendix 5.2.
5.1.1.Two limit level exceedances were recorded at M4a on
20 and 27 July 2010 during restricted hours. The traffic noise from Island
Eastern Corridor was the major noise source contributed in the exceeded noise
levels. The work undertaken was
complied with the conditions under valid Construction Noise Permit no.
GW-RS0371-10 during the measurement. At such, it was
considered as not project related exceedances.
Reviewed the past
monitoring results and observation at Station M4a, the monitoring location at
Causeway Bay Community Centre is facing and closed to the Island Eastern
Corridor. Traffic noise is the major noise source obtained in the monitoring
that cannot be reflected the
fact of the construction noise from the construction site. Victoria Centre
(Station ID: M4b) is proposed as alternative noise monitoring station from
August 2010.
Contract
no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at
HKCEC and Contract no. HK/2009/02 - Wan Chai Development Phase II – Central –
Wan Chai Bypass at WanChai East
5.1.4.
The commencement of
marine construction works for Contract no. HK/2009/01 and HK/2009/02 were
commenced in July 2010. The proposed division of noise monitoring
stations are summarized in Table 5.2 below.
Table 5.2
Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.5.
Day timeDaytime and evening
period noise monitoring was conducted at the Harbour Road Sport Centre in the
reporting month. Due to the marine works
undertaken in evening time from 12 July 2010, noise monitoring during evening
time was conducted from 13 July 2010.
5.1.6.
Three Three limit level
exceedances were recorded at M1a - Harbour Road Sports Centre on 4, 10 and 16
November 2010 during the evening time period.limit level exceedances
were recorded 11071714AugustSeptember during
construction works at evening time for Contract no. HK/ 2009/02
in reporting month. Major noise source was contributed from
Tonnochy Road and water sport competition at Wan Chai Training Swimming Pool. The
dredging work was complied with the conditions under valid Construction Noise
Permit no. GW-RS0132RS0777-10 during the measurement.
Contract no. HY/2009/15 - Central-Wanchai Bypass
– Tunnel (Causeway Bay Typhoon Shelter Section)
5.1.7.
The noise monitoring for HY/2009/15 was commenced on 10 November 2010. The
proposed division of noise monitoring stations are summarized in Table
5.3 below.
Table 5.3 Noise Monitoring Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
5.1.8.
Noise monitoring results measured in this reporting
period are reviewed and summarized. No
exceedance was recorded in reporting month.. Details of noise monitoring
results and graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/11
– Central – Wanchai Bypass, North Point Reclamation
5.2.1.
The proposed division of real-time noise monitoring stations are
summarized in Table 5.4 below. Real time noise monitoring for the
filling works under contract no.
HY/2009/11 was commenced on 5 October 2010
Table 5.4 Real Time Noise Monitoring Station
for Contract no. HY/2009/15
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section
Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison
Centre |
5.2.2.
No exceedance was recorded during the daytime
period. In
contrast, exceedances were recorded between 1900 and 2300 hours throughout the reporting
month and between 2300 and 0700 on the next day. Details of real time noise
monitoring results and graphical presentation can be referred to Appendix 5.5 .
It is concluded as not related to the Project
works. However, baseline noise level at M1 is 60.1 dB(A) which is needed to be
reviewed.
Contract
no. HY/2009/11 – Central – Wanchai Bypass, North Point Reclamation
5.3.1.
The major construction activities of Contract no.
HY/2009/11 were dredging works and filling works in the reporting month. Air monitoring had been
commenced on 11 August 2010. The proposed division of air monitoring stations
are summarized in Table 5.5 below.
The major construction activities of Contract no.
HY/2009/11 was dredging works in the reporting month. No major dust impact is anticipated to be caused by
the dredging works. Therefore, no
air monitoring was conducted in the reporting month.
Air monitoring will be
commenced from the filling work for
Contract no. HY/2009/11. The proposed division of air
monitoring stations are summarized in Table 5.3 below.
Table 5.35
Air Monitoring Stations for Contract
no. HY/2009/11
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
Causeway Bay Community Centre |
24-hour electricity
supply in CMA1b – Oil Street Community Liaison Centre was connected on 22 September 2010. Due to no 24-hour
electricity supply in CMA1b – Oil Street Community Liaison Centre, only 124can be conductedwas commenced on 27
September 2010
5.3.2.
No exceedance was recorded in the reporting month. Details of air monitoring
results and graphical presentation can be referred in Appendix
5.3.
5.3.1.One
limit level exceedance was recorded at CMA1b on 24 August 2010. Investigation found that the exceedance was not related to the construction activitiesNo exceedances wasexceedances were recorded in the
reporting month
Contract
no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at
HKCEC
5.3.3.
Air monitoring will be commenced from
the land-filling
work for Contract no. HK/2009/01. The proposed division of air monitoring
stations are summarized in Table 5.64
below.
Table 5.46
Air
Monitoring Stations
for Contract
no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
CMA6a |
Future AECOM site office at Work Area 1 |
Contract
no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at
WanChai East
5.3.4.
Air monitoring will be commenced from the
land-filling work for Contract no. HK/2009/01. The proposed division of air
monitoring stations are summarized in Table 5.7 below.Air monitoring
will be commenced from the
filling work for Contract no. HK/2009/02. The
proposed division of air
monitoring stations are summarized in Table 5.5 below.
Table 5.57
Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section)
5.3.5.
Air monitoring will be commenced from the land filling work for Contract no.
HY/2009/15. The proposed division
of air monitoring stations are summarized in Table 5.8 below.
Table 5.8 Air Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site office at Wanchai Waterfront Promenade |
Contract
no. HY/2009/11 – Central – Wanchai Bypass, North Point Reclamation
5.4.1.
The proposed division of water
monitoring stations for Contract no. HY/2009/11 are summarized in Table
5.6 9 below:
Table 5.6 9 Water Monitoring Stations for Contract no. HY/2009/11
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
Cooling Water Intake |
|||
C8 |
City Garden |
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
Contract
no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at
HKCEC
5.4.2.
Water monitoring for Contract no. HK/2009/021 was commenced on 23
July 2010. Due to the commencement
of dredging work for Contact no. HK/2009/02,
water monitoring
stations for Contract no. HK/2009/01 were commenced on 8
July 2010. Installations of silt screen and silt curtain were
completed in the reporting month. The proposed division of water
monitoring stations are summarized in Table 5.107 below.
Table 5.710
Water Monitoring Stations for Contract no. HK/2009/01
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
Kowloon South |
834150.0 |
818300.3 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
Kennedy Town |
830750.6 |
816030.3 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Wan Chai Tower and Great
Eagle Centre (Eastern) |
835932.8 |
815888.2 |
C4w |
Wan Chai Tower and Great
Eagle Centre (Western) |
835629.8 |
815889.2 |
Remarks:
The water monitoring stations for
the dredging works under Contract No. HK/2009/01 should also include WSD9,
WSD17, WSD 21 and C5 if water quality monitoring at these locations have not
been carried out by others. Similarly, the water monitoring stations for the
dredging works under Contract No. HK/2009/02 should also include WSD7, WSD9,
WSD17, WSD 19, C1, C2, C3 and C4 if water quality monitoring at these locations
have not been carried out by others.
Contract
no. HK/2009/02 - Wan Chai Development Wan Chai Development Phase II – Central –
Wan Chai Bypass at WanChai East
5.4.3.
Water monitoring for Contract no.
HK/2009/02 was commenced on 8 July 2010. Installations of silt
screen and silt curtain were completed in the reporting month.
The proposed division of water monitoring stations are summarized
in Table
5.8 11 below.
Table 5.8 11 Water Monitoring Stations for Contract no. HK/2009/02
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
Cooling Water Intake |
|||
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
Remarks:
The water monitoring stations for
the dredging works under Contract No. HK/2009/01 should also include WSD9,
WSD17, WSD 21 and C5 if water quality monitoring at these locations have not
been carried out by others. Similarly, the water monitoring stations for the
dredging works under Contract No. HK/2009/02 should also include WSD7, WSD9,
WSD17, WSD 19, C1, C2, C3 and C4 if water quality monitoring at these locations
has not been carried out by others.
Contract no. HY/2009/15 - Central-Wanchai Bypass
– Tunnel (Causeway Bay Typhoon Shelter Section)
5.4.4.
Due to the commencement of the maintenance dredging
on 10 November 2010, water quality monitoring for Contract no. HY/2009/15 was commenced on 9 November 2010. The proposed division of water
monitoring stations are summarized in Table 5.12
below.
Table 5.12 Water
Monitoring Stations for Contract no. HY/2009/15
Station Ref. |
Location |
Easting |
Northing |
Cooling
Water Intake |
|||
C6 |
Excelsior
Hotel |
837009.6 |
815999.3 |
C7 |
Windsor House |
837193.7 |
816150.0 |
5.4.1.
The access to WSD7 is
needed to via the gates that are locked and under the control of LCSD between
1900hrs and 0700hrs from 10 July 2010. The approval of access permission had been obtained from LCSD for the access to WSD7 in Mid-August 2010. However, due to the wrong locking order of the series pad locks at the gate, water quality monitoring could not be conducted
on 30 July, 18 and 25 August 2010.The
access to WSD7 is needed to via the gates that are locked and
under the control of LCSD between 1800hrs and 0800hrs from 10 July 2010. Due to
no access permission obtained from LCSD in this reporting month, water
monitoring cannot be conducted at WSD7 on
10/7/2010 at mid-flood, 14/7/2010 at
mid-flood and mid-ebb, 18/7/2010 at mid-flood and 19/7/2010 at mid-ebb. LCSD
has been liaised to request obtaining the
access permission in the reporting month.
Due to the construction and maintenance works
of the silt screen cover at C4e and C4w conducted by Chun Wo & Leader JV on
14/7/2010, no water monitoring was conducted at these stations during the
mid-ebb.
5.4.1.
Due toDue to theDue to Strong Wind Signal
No. 3, no, black rainstorm warning and redamber
rainstorm warning in force on 28 July 2010 and 28 June5 AugustSeptember 2010 respectively mid-ebb
and 28 July 2010 mid-flood, strong Wind Signal No.
3 announced on 21/7/2010, no
water monitoring was conducted in these
days. at C1 to C4 on 28 July 2010 at mid-ebb tide and on 28
July and 5 August at
mid-flood tide asere on 5 September 2010 at
mid-flood tide
5.4.5.
Water monitoring results measured in
this reporting period are reviewed and summarized. Details of water quality monitoring results and graphical
presentation can be referred in Appendix
5.43.
Table 5.9 13 Summary of Water Quality Monitoring Exceedances in Reporting
Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
WSD17 |
0 |
0 |
0 |
1 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C8 |
0 |
0 |
0 |
1 |
2 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
|
C9 |
0 |
0 |
0 |
1 |
2 |
0 |
0 |
0 |
1 |
1 |
1 |
0 |
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
|
WSD20 |
0 |
0 |
0 |
1 |
2 |
1 |
0 |
0 |
1 |
1 |
1 |
1 |
|
WSD7 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C3 |
0 |
0 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
|
C4e |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
2 |
Hy/2009/15 |
C6 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
1 |
4 |
9 |
3 |
0 |
0 |
3 |
4 |
5 |
7 |
Contract
no. HY/2009/11 – Central – Wanchai Bypass, North Point Reclamation
5.5.1.
No inert and Nnon-inert C&D
waste and marine sediment werewas disposed of in
the reporting month. Details of the waste flow table are summarized in Table
5.1014.
Table 5.14 Details of
Waste Disposal for Contract no. HY/2009/11
Table 5.10 Details of Waste Disposal for Contract no.
HY/2009/11
Waste
Type |
Quantity this month, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal) |
(Bulk Volume) |
(Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) |
(Bulk Volume) |
117,500 (Bulk Volume) |
East of Sha Chau |
5.5.1.
As further checked and
reviewed the cumulative quantity of
marine sediment (Type 1 – Open Sea Disposal (Dedicate Sites) &
Type 2 – Confined Marine Disposal), the quantity and
cumulative quantity in May 2010 shall be
3,000m3 and 46,500m3. Thus,
the cumulative quantity is 74,500 in this
reporting month.
5.5.2.
There were marine sediments Type 1 –
Open Sea Disposal and Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2
– Confined Marine Disposal marine sediment disposed in the reporting month. The
maximum dredging rates
in North Point Reclamation (NPR) Shoreline Zone is 1,52,000m3 per
day in the reporting month, which is is complied with the
criteria
recommended
maximum dredging rate, 6000m3 listed in Table 5.102 of FEP-01/356/2009IA
Report Register No. AEIAR-125/2008.
Contract no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai
Bypass at HKCEC
5.5.3.
Inert and non- inert C&D waste
were disposed of for the site preparation works in this
reporting month. Details of the waste flow table are summarized in Table
5.1115.
Table 5.1115 Details
of Waste Disposal for Contract no. HK/2009/01
Waste
Type |
Quantity this month, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
777.43 |
1,385.9 |
TKO134 |
Inert C&D materials recycled |
0 |
0 |
N/A |
Non-inert C&D materials disposed |
14.92 |
105.42 |
SENT Landfill |
Non-inert C&D materials recycled |
|
|
N/A |
Chemical waste disposed |
0.22 |
|
N/A |
Marine Sediment (Type 1 – Open Sea Disposal) |
(Bulk Volume) |
52,497 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) |
(Bulk Volume) |
(Bulk Volume) |
|
The Contractor clarified
the cumulative quantity shall be 12.92m3
non-inert C&D material disposed in last reporting month. Thus,
the sum of cumulative of non-inert C&D
material is 21.96m3 in
this reporting month.
5.5.4.
There were
marine sediments Type 1 – Open
Sea Disposal disposed in the reporting month. The maximum dredging
rate is 700m3 per day in the
reporting month, Due to the revised the density value of inert and non-inert
C&D material, the contractor clarified the cumulative quantity of inert C&D material
and non-inert C&D material shall be 608.47m3 and 90.5m3
respectively
disposed in last reporting month.
5.5.5.
There were marine sediments Type 1 – Open Sea
Disposal and Type
1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal
marine sediment
disposed in the reporting month. The maximum dredging rate in HKCEC1 and Cross Harbour Water Mains
marine work zone marine work zones are 540m3 per day respectively, which are complied
with the recommended maximum dredging rate, 1500m3 per day listed in
Table 2 of FEP-02/356/2009. which is complied with the
criteria listed in Table 5.10 of EIA Report Register
No. AEIAR-125/2008.
Contract no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan
Chai Bypass at WanChai East
5.5.6.
Inert and non- inert C&D waste
were disposed of for the site preparation works in this
reporting month. Details of the waste flow table are summarized in Table
5.1216.
Table 5.1216 Details
of Waste Disposal for Contract no. HK/2009/02
Waste
Type |
Quantity this month, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
|
|
TKO137 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
|
|
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal) |
(Bulk Volume) |
(Bulk Volume) |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) |
(Bulk Volume) |
(Bulk Volume) |
East of Sha Chau |
5.5.7.
There were
marine sediments Type 1 – Open
Sea Disposal disposed in the reporting month. The
maximum dredging rate is 1,,490m3 per day in the
reporting month,There
were marine sediments Type 1 – Open Sea Disposal disposed in the reporting
month. The maximum dredging rate in Wan
Chai Reclamation (WCR) marine work zone 407m3
per day, which is complied with the recommended maximum dredging
rate, 6000m3 listed in Table 2 of FEP-03/356/2009.
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section)
5.5.8.
No inert and non- inert C&D wastes were disposed of in this
reporting month. Details of the waste flow table are summarized in Table
5.17.
Table 5.17 Details of
Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity
this month, m3 |
Cumulative
Quantity-to-Date, m3 |
Disposal /
Dumping Grounds |
Inert C&D materials
disposed |
NIL |
NIL |
N/A |
Inert C&D materials
recycled |
NIL |
NIL |
N/A |
Non-inert C&D
materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials
recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Marine Sediment (Type 1
– Open Sea Disposal) |
NIL |
NIL |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) |
12,390 (Bulk Volume) |
12,390 (Bulk Volume) |
East of Sha Chau |
5.5.9.
In the reporting month, there was marine sediment Type 1 – Open Sea
Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal marine
sediment
disposed from
the maintenance dredging works at PMA,
TCBR2 and TCBR3 for mooring and anchorage rearrangement. No more than one closed dredger and no concurrent dredging at the marine zones for PMA mooring and anchorage rearrangement, TCBR2 and TCBR3 was
conducted in the reporting month.
5.5.10. Referring
to the EPD’s comments in Appendix 2.1, the dredging rate
for the maintenance dredging should be same as or less than that stipulated in
EP-356/2009 within the Temporary Causeway Bay Reclamation (TCBR) marine work zone. Thus, the maximum dredging
rate, 1,290 m3
per day in the
reporting month
is complied with the recommended maximum dredging rate, 6000m3 as
stipulated in EP-356/2009 within the marine zones at TCBR.
6.0.1. The Event Action Plan for construction noise, air quality and water quality are presented in Appendix 6.1.
Contract no. HY/2009/11 – Central
– Wanchai Bypass, North Point Reclamation
6.1.1.
No exceedance was
recorded in the reporting month. Due to the excavation and
breaking works undertaken next to the monitoring station at M5b - City Garden
by the other project during the noise monitoring, two limit level exceedances
were recorded on 10 and 16 November 2010 at the day time period. It was considered as not
project related exceedances.
6.1.1.Two limit level
exceedances were recorded at M4a on 20 and 27 July 2010 during restricted
hours. The traffic noise from Island Eastern Corridor was the major noise
source contributed in the exceeded noise levels. The
work undertaken was complied with the
conditions under valid Construction Noise Permit no. GW-RS0371-10 during the
measurement. At such, it was considered as not project related
exceedances.Two action level exceedances were
recorded due the receipt
of noise complaints dated 31 July
and 12 August 2010 regarding the noise nuisance generated from the dredging works at North Point.
6.1.1.
Contract no.
HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC
6.1.2.
No exceedance was
recorded in the reporting month.
Contract no. HK/2009/02 - Wan Chai
Development Phase II – Central – Wan Chai Bypass at WanChai East
6.1.3.
Three Three limit level
exceedances were recorded at M1a - Harbour Road Sports Centre on 4, 10 and 16
November 2010 during the evening time period. Major noise source was
contributed from Tonnochy Road and water sport competition at Wan Chai Training
Swimming Pool. The dredging work was complied with the conditions under valid
Construction Noise Permit no. GW-RS0777-10 during the measurement. It was considered as not
project related exceedances. limit level exceedances
during evening time were recorded in reporting monthAugust September . Major
noise source was contributed from Tonnochy Road and
water sport competition at Wan Chai Training Pool. The
dredging work was complied with the conditions under valid Construction Noise
Permit no. GW-RS0132-10 during the
measurement. It is concluded as not
related to the Project works.
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section)
6.1.4.
No exceedance was recorded
in the reporting month.
Contract no. HY/2009/11
– Central – Wanchai Bypass, North Point Reclamation
6.2.1.
No exceedance was recorded during daytime period in the reporting month. Only dredging work was conduced
during the period
of 1900-2230 with valid CNP no. GW-RS0870-10. In contrast, exceedances
were recorded during
evening time
and between 2300 and 0700 on the next day throughout the reporting month. Investigation found that
the major noise impacts between 1900 and 2300 hours and between 2300 and 0700
on the next day were
arising from the traffic noise at the Island Eastern Corridor. As
such, the exceedances were concluded not project related.
6.3.1.
No exceedance was
recorded in the reporting month.However, baseline noise level at M1 is 60.1dB(A) which
is needed to be reviewed in next reporting month.
No air monitoring was
conducted in this reporting period.
6.3.1.
No
exceedance was recorded in the reporting month.
6.3.1.
One
action level of 1 hour TSP was recorded at station CMA1b – Oil Street Community
Liaison Centre on 24 August 2010. Burning joss paper activity was observed near
the Oil Street Community Centre between 23 and 25 August 2010 morning. It was
no dust generating construction activities undertaken near the station CMA1b during the air monitoring. Considering no further exceedance of 1 hour TSP was recorded at
the same day, it was concluded as an invalid exceedance.
Contract
no. HY/2009/11 – Central – Wanchai Bypass, North Point Reclamation
6.4.1.
ReferringRReferringeferringReferring to the
exceedances recorded shown in Table 5.9, the occasionally action
and limit level exceedances of turbidity and suspended solid were recorded at WSD15, WSD17, C8
and C9.
6.4.2.
was Since
was fthere were numerous unknown outfalls from the
nearby coastal area closed to the cooling intakes C8 and C9, it causes the potential for accumulation of
pollutants near the intakes and may lead to potential water quality
deterioration at the seawater intake points. It was concluded as natural variation and not
projected
related exceedances.
6.4.3.
Silt screen at C8 has been dismantled on 16 September 2010 and contractor will modify and install new silt screen in which subject to the approval of
schedule and agreement between the cooling water intake’s owners.
6.4.1.
Since the
natural flow during the flood tide indicated that the source of impact was
located at the upstream of the marine works area, turbidity
and 30 July8 Septembermid-ebbmid-ebb
6.4.1.
6.4.4.
SS exceedances recorded at WSD17, C8 and C9 during mid-flood were
concerned as not related to Project.1130,at
WSD15 on 10 September 2010.
6.4.5.
Reviewed the trend of overall results at all
monitoring stations nearer the marine work area, the SS exceedance recorded at WSD15 on 12 November 2010 at mid-ebb tide while low SS value was
recorded without exceeded the action and limit level. Thus, this SS
exceedance was
considered not related to the Project works.
The data were compared and reviewed that SS level at
the nearest monitoring stations to the marine works area were below the action
and limit level. It is concluded the exceedances not related to the Project
works.
6.4.1.SS exceedances were recorded at and
at 94AugustSeptemberInvestigation found that sThe
data were compared and reviewed that SS level at
the nearest monitoring stations to the marine works area were below the action and limit level. It is concluded the
exceedances not related to the Project works.ilt
screen washing was commenced during sampling. It
is concluded the exceedances not related
to the Project works.Occasional SS exceedances were occurred at Stations WSD9,
WSD10, WSD15 and WSD17. Investigation was found that the exceedances were due to the natural
variation and not related to the Project works.
Frequent action
and limit level exceedances
of dissolved oxygen were
recorded at Stations WSD9, WSD10,
WSD15, WSD17, C8 and C9 stations in the reporting month. The data were compared and reviewed that dissolved oxygen concentrations
at the nearest and furthest monitoring stations to the marine works area were low.
It was concluded as natural variation and no projected
related exceedances. It was concluded that the
exceedances were due to natural variation and not related to the Project works.
Contract
no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at
HKCEC
6.4.6.
Referring to all exceedances recorded at WSD7, WSD19
and WSD20, there
was no exceedance recorded at the monitoring stations nearer the marine work area for
Contract HK/2009/01. Those exceedances were considered as not related to
the Project works.
6.4.7.
Occasional turbidity and SS exceedances were
recorded at stations C3 and C4e. In view of silt screen and silt curtain were in proper condition undertaken at HKCEC marine works zone, it was concluded as not
project related exceedances.
Since the dredging works was commencement on 23
July 2010, the exceedances recorded at the monitoring stations relevant to
Contract no. HK/2009/01 were considered not related to the Project works. No
exceedance was recorded after the commencement of the dredging work.Contract
no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at
WanChai East
6.4.1.
SS exceedances were
recorded at WSD21 on 17 November and at C5w on 5, 15 and 17 November 2010. Action and
limit level exceedances of dissolved
oxygen were recorded at Stations C5e, C5w and
WSD21 in the reporting month. The
data were compared and reviewed that dissolved oxygen concentrations
at the nearest and furthest monitoring stations to
the marine works area were low. It was concluded that the
exceedances were due to natural variation and not related to the Project works.
6.4.8.
Investigation for the SS and dissolved
oxygen exceedances recorded at relevant monitoring found that the
condition of silt screen and silt curtain are was in proper
condition and daily dredging rate are were complied with
EP condition when
the turbidity and SS exceedances recorded at WSD21.,
Besides, the
additional measure of additional silt curtain is deployed to protect the monitoring
stations WSD17, C5e and C5w. Thus, tthe he exceedances were
considered due toas
natural variation or
screen washing at the station and
not related to the Project.
6.4.9. Summary for notification of exceedances can be referred to Appendix 6.2.
6.5.1. There was no non-compliance from the site audits in the reporting period. The observations and recommendations made in each individual site audit session were presented in Section 8.
6.5.2. No project-related non-compliance from monitoring was recorded in the reporting month.
6.6.1. There was no particular action taken since no project-related non-compliance was recorded from the site audits and environmental monitoring in the reporting period.
7.0.1.
According to Condition 3.4 of the
EP-356/2009, this section addresses the relevant cumulative construction impact
due to the concurrent activities of the current projects including the Central Reclamation
Phase III, Central-Wanc Chai
Baypass
and Island Eastern Corridor Link projects.
7.0.2.
From the Monthly EM&A report (AugustOctober July 2010)
of Central Reclamation Phase III (CRIII) the key works in August SeptemberNovember 2010 are as follows:
·
Type A
filling in FRAW and FRAE above +2.5mPD;
·
Type A filling in FRAW
and FRAE above +2.5mPD;
·
Type A filling in FRAW
and FRAE above +2.5mPD
·
General filling works
above +2.5mPD in IRAE
·
Surcharging in FRAW and
FRAE
·
Construction of
cantilever slab at caisson
·
Pile cap and base slab
construction at Culvert F
·
Construction of storm and
foul drainage and gullies in hinterlands for Road P2, Road D7, and Road D9
·
Construction of GPO
boundary wall
·
·Road P2 Underpass ramp
structures
·
Precasting for retaining
wall (offsite)
·
Installation of cooling
mains discharge pipes in FRAE and FRAW
·
Diaphragm wall and
barrettes for CWB Works
·
Bulk excavation to
formation level at CWB works
·
Construction of CWB
structure
·
Disposal of material
off-site to Government fill banks
·General filling works above +2.5mPD in IRAE;
·Surcharging in FRAW and FRAE;
·Construction of cantilever slab at caisson;
·Pile cap and base slab construction at Culvert F;
·Construction of storm and foul drainage and gullies
in hinterlands for Road P2, Road D7, and Road D9;
·Construction of watermains at Road D7;
·Road P2 Underpass ramp structures;
·Precasting for retaining wall (offsite);
·Installation of cooling water mains for Tamar
Development Project;
·Installation of cooling mains discharge pipes in
FRAE;
·Diaphragm wall and barrettes for CWB Works;
·Excavation to formation level at CWB works;
·Construction of CWB structure; and
·Disposal of material off-site to Government fill
banks
7.0.3.
According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activities under Wan Chai Development Phase II
were the
dredging and filling works at North Point Reclamation Shoreline Subzone (NPR2E)
and (NPR1) respectively, the dredging and rock-filling at Wan Chai Reclamation
Shoreline Subzone (WCR1) and dredging at HKCEC1 and cross-harbour water mains
in the reporting month. The major environmental impact was water quality
impact at North Point and Wan Chai.
7.0.1.
General
filling works above +2.5mPD in IRAE;
·
Surcharging
in FRAW and FRAE;
·
Construction
of cantilever slab at caisson;
·
Pile
cap and base slab construction at Culvert F;
·
Construction
of storm and foul drainage and gullies in hinterlands for Road P2, Road D7, and Road
D9;
·
Construction
of watermains at Road D7;
·
Road
P2 Underpass ramp structures;
·
Precasting
for retaining wall (offsite);
·
Installation
of cooling water mains for Tamar Development Project;
·
Installation
of cooling mains discharge pipes in FRAE;
·
Diaphragm
wall and barrettes for CWB Works;
·
Excavation
to formation level at CWB works;
·
Construction
of CWB structure; and
·
Disposal
of material off-site to Government fill banks
7.0.1.
The major environmental
impacts generated from the Central Reclamation Phase III were located along the
coastline of Central and Admiralty while dredging works at NPR2E, WCR1, HKCEC1 and cross-harbour
water mains
were in operation in this reporting month. Since no Project-related exceedance
was recorded from the Project in the reporting month, it is evaluated that the cumulative
construction impact from the concurrent projects including Wan Chai Development
Phase II and Central Reclamation Phase III was insignificant.According to the construction programme of Central-Wan
Chai Baypass and Island Eastern Corridor Link projects, the
major construction activity under Wan Chai
Development Phase II was the dredging works at
North Point Reclamation Stage 1(NPR1), Wan Chai Reclamation Stage 1(WCR1)
and Hong Kong Convention and
Exhibition Centre Stage 1(HKCEC1) in the reporting month. The major
environmental impact was water quality impact at North Point and Wan Chai. No
major construction activities were undertaken in the Central-Wan Chai Baypass
and Island Eastern Corridor Link
projects.
7.0.4.
The major environmental impacts generated
from the Central Reclamation Phase III were located along the coastline of Central and Admiralty while dredging works at NPR1, WCR1 and HKCEC1 were in operation in this reporting month.
The dredging works was just commenced at
WCR1 and HKCEC1 in this reporting month. Beside, water quality mitigation measures were
properly in place for the dredging works in this reporting month. No project –related
exceedance were recorded. Thus, it is
evaluated that the
cumulative construction impact from the concurrent projects
including Wan Chai Development Phase II and Central Reclamation Phase III was insignificant.
8.0.1.
During this reporting month,
weekly environmental site audits were conducted for Contracts no. HY/2009/11,
HK/2009/01 and, HK/2009/02 and HY/2009/15. No non-conformance was
identified during the site audits.
8.0.2.
Five Four site inspections
for Contract no. HY/2009/11 were carried out during this reporting
periodon
2, 9, 17 and 23 November 2010. The results of these inspections and
outcomes are summarized in Table 8.1.
Table
8.1 Summary
of Environmental Inspections for
Contract no. HY/2009/11
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
101102_01 |
2-Nov-10 |
The framework of silt curtain should be maintained before dredging |
Maintenance the framework of silt curtain |
Completion as observed on 17-Nov-10 |
101102_02 |
2-Nov-10 |
Collect refuse at Sai Wan Ho and Quarry Bay
before silt curtain removement |
Collect refuse before silt screen removement |
Completion as observed on 9-Nov-10 |
101117_01 |
17-Nov-10 |
Stockpile shall be covered by fabric fibre or tarpaulin |
Cover stockpile by tarpaulin |
Completion as observed on 30-Nov-10 |
101123_01 |
23-Nov-10 |
The housekeeping, include rubbish collection is
needed to improve |
Improve house keeping |
Completion as observed on 30-Nov-10 |
8.0.3.
Five Four site inspections
for Contract no. HK/2009/01 were carried out during this reporting period. The results of these inspections and
outcomes are summarized in Table 8.2.
Table 8.2 Summary
of Environmental Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
101103_01 |
3-Nov-10 |
Trees at Tsim ShaTsui shall be fence-off and
well protected |
Provided fencing for tree protection |
Completion as observed
on 10-Nov-10 |
101103_02 |
3-Nov-10 |
Design of sedimentation tank shall be modified to
enhance the effectiveness of desilting |
Re-design
the sedimentation tank |
Completion as observed
on 10-Nov-10 |
101103_03 |
3-Nov-10 |
Dust control shall be enhanced at TST |
Provided water spraying on the dusty surface |
Completion as observed
on 10-Nov-10 |
101110_01 |
10-Nov-10 |
Minimize the stockpile storage of C&D waste
near the trees at Tsim Sha Tsui |
Relocation of the stockpile material away from the
trees |
Completion as observed
on 24-Nov-10 |
101118_01 |
18-Nov-10 |
Noise emission label for hand-held breaker shall be
displayed |
Proper aadhere noise emission label on the equipment |
Completion as observed
on 24-Nov-10 |
101124_01 |
24-Nov-10 |
Design of sedimentation tank at Tsim Sha Tsui
should be further improved. |
Improvement works had been conducted. |
Completion as observed
on 1-Dec-10 |
8.0.4.
Five Five site inspections
for Contract no. HK/2009/02 were carried out during this reporting period. The results of these inspections and
outcomes are summarized in Table 8.3.
Table 8.3 Summary
of Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
101028_01 |
28-Oct-10 |
Housekeeping needs to be improved on Tsang Leung
Kee 6 as dust spreading was observed |
Proper maintain the house keeping at the site |
Completion as observed on 4-Nov-10 |
101028_02 |
28-Oct-10 |
Stockpile was observed not covering well |
Covered or spray water on the dusty stockpile |
Completion as observed on 4-Nov-10 |
101028_03 |
28-Oct-10 |
Floating Rubbish was observed near the
seawall. |
Regular clearance of the floating rubbish |
Completion as observed on 4-Nov-10 |
101028_04 |
28-Oct-10 |
The enclosure for the grouting plant was observed not
functioning well and dust leakage was observed |
Proper enclosed the grouting plant |
Completion as observed on 4-Nov-10 |
101028_05 |
28-Oct-10 |
Water spreading was observed during
the bore pile washing |
Provided preventive measures to avoid water
spreading to the road. |
Completion as observed on 4-Nov-10 |
101104_01 |
4-Nov-10 |
Contaminated soil should be
cleared and deposited as chemical waste with proper procedure |
Proper clearance of
contaminated soil |
Completion as observed on 11-Nov-10 |
101104_02 |
4-Nov-10 |
It is recommended that
the grab dredger should be opened below sea level during the rock filling
works for seawall construction. |
Immediate improvement practices was done |
Completion as observed on 11-Nov-10 |
101111_01 |
11-Nov-10 |
Stockpile shall be covered better by fabric fibre or tarpaulin. |
Covered or spray water on the dusty stockpile |
Completion as observed on 18-Nov-10 |
101111_02 |
11-Nov-10 |
Drip tray for the generator shall be plugged tightly |
Well plugged drip tray |
Completion as observed on 18-Nov-10 |
101118_01 |
18-Nov-10 |
Opening of silt curtain shall be always closed |
Closed silt curtain was observed during the site
audit |
Completion as observed on 25-Nov-10 |
101118_02 |
18-Nov-10 |
Silt curtain shall be well maintained and enhance
the weight to avoid floating up |
Improvement work of silt curtain had been done |
Completion as observed on 25 |
101118_03 |
18-Nov-10 |
Chemical containers at WSD pumping station should
be provided with drip tray |
Drip tray
had been provided underneath the chemical containers. |
Completion as observed on 25 |
101125_01 |
25-Nov-10 |
Stockpile shall be stored away from drip tray to
prevent contamination |
Relocation of stockpile to avoid the soil
contamination |
Completion as observed on 2-Dec-10 |
101125_02 |
25-Nov-10 |
All plugs of drip tray shall be checked and
maintenance frequently |
Proper condition of the drip tray during the site audit |
Completion as observed on 2-Dec-10 |
8.0.5.
Four site inspections for Contract no. HY/2009/15
were carried out on 2, 9, 16 and 23
November 2010. The
results of these inspections and outcomes are summarized in Table 8.4.
Table 8.4 Summary of
Environmental Inspections for Contract no. HY/2009/15
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
101109_03 |
9-Nov-10 |
Proper care all trees
inside the construction site |
Proper care has been taken to all trees inside the
construction site |
Completion as observed on 16-Nov-10 |
101116_01 |
16-Nov-10 |
Dust generated by
trunks at the site office area when moving. The contractor is reminded to
clear the dust |
Clearance the dust at the site
office |
Completion as observed on 23-Nov-10 |
101116_02 |
16-Nov-10 |
Silt curtain shall be
mounted between dredgers and barge |
Mounted silt curtain
between dredgers and barge |
Completion as observed on 23-Nov-10 |
101123_01 |
23-Nov-10 |
The contractor is
reminded to place a geotextile under the gully to prevent any tiny C&D
material washed directly into drainage system |
Place a geotextile under the gully |
Completion as observed on 30-Nov-10 |
9.0.1.
No Two noise complaints was were received
dated 31 July 2010
and 12 August 2010. The complaint dated 31 July 2010 was
regarding the noise nuisance generated
from dredging work adjacent
to Oil Street and three construction plantin the
reporting month. In the last reporting month, the complaint log no. 100615 recorded on 15 June
2010 was
subsequently considered as an enquiry. RSS clarified that the
above issue was logged as an enquiry rather than a complaint in Highway
Department’s record. s were operated
concurrently. Noise monitoring results
at stations M4b and M5b during the daytime and evening time were
reviewed and no exceedanced was recorded on 27 July and 3 August 2010. The PME used in the dredging works were checked and
confirmed compliance with the EP and
valid CNP no.
GW-RS0371-10.No environmental complaint was received in the reporting month.Two environmental
complaints were received on 8 and 10 November 2010 in the reporting month.
9.0.2.
The visual complaints dated 8 November 2010 was regarding the floating
refuse around
the seaside silt screen outside the WSD freshwater intake pump at Sai Wan Ho (Water Monitoring Station ref. WSD15). Follow-up action had been
immediately carried out to check and clear the floating refuse around the
seaside silt screen after receipt of the complaint. Removal of seaside silt
screen outside the WSD freshwater intake (WSD15) by contractor HY/2009/11 was
checked and confirmed dated 9 November 2010.
9.0.3.
The other noise complaint dated 10 November 2010
was received from the Harbour Height Management Office. Their resident
complained on the noise nuisance generated from the power mechanical equipment
during the period from 0700 to 2200. Investigation found that
the PME used
in restricted hours were checked and confirmed compliant with the valid CNP no.
GW-RS0870-10.
No exceedance was recorded during the impact noise monitoring at the nearest noise
monitoring station at Victoria Centre on 4 and 10 November 2010, The complaint was
considered not valid from the CNP and EP point of view.
9.0.1.
Another
noise complaint dated
12 August was received from Harbour Heights (Management) Limited. They received their resident complained on
the noise nuisance generated from the dredging works at the marine
works area adjacent to the Habour
Height during the period from 0700 to 2200. Reviewed the noise monitoring results at noise monitoring station at
Victoria Centre and City Garden during daytime and evening time, no exceedance
was recorded on 10 and 17 August 2010. The construction plants used
in restricted hour were complied with the valid CNP no. GW-RS0371-10.
9.0.1.
Based
on the investigation, these
complaints were
considered not valid from the CNP and EP point of view.
9.0.4.
The details of cumulative
complaint log and updated summary of complaints are
presented in Appendix 9.1.
9.0.5. Cumulative statistic on complaints and successful prosecutions are summarized in Table 9.1 and Table 9.2 respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
|
|
Project-to-Date |
|
Table 9.2 Cumulative Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.
10.0.2. The scheduled construction activities and the recommended mitigation measures for the coming month are listed in Table 10.1.
Table
10.1 Construction
Activities and Recommended Mitigation Measures in Coming Reporting Month
Contract
No. |
Key Construction Works |
Recommended
Mitigation Measures |
HY/2009/11 |
·
Dredging
works; ·
Reclamation
works; ·
Construction
& installation of Seawall Block; ·
Floating
Out of Caisson Seawall; ·
Drainage
Construction works; ·
Construction
of coping; and
·
|
·
To avoid concurrent noisy operation ·
To locate the plant and equipments far away
to the noise sensitive receivers ·
Daily visual inspection of silt screen and silt curtain to ensure its
operation properly ·
Daily clearance of floating debris behind the silt screen |
HK/2009/01 |
·
Installation of pipe piles of P1 Wall at West
Bridge; ·
Removal of the staging platform & staging
piles of trial bored pile; ·
Dredging works and removal of rock armour for
existing sloping seawall at HKCEC water channel; ·
Reclamation works starts in the HKCEC water
channel; ·
Dredging works for cross harbour watermains; ·
Commencement of removal of Wan Chai seawall
(pipeline connection points); ·
Commencement of temporary jetty construction; ·
Implementation of TTM scheme for trial pit at
Convention Avenue (Area A2); ·
Implementation of TTM scheme for pipe laying at
Convention Avenue (Area A1-1) for cooling water main and Harbour Road (Area
A5-1) for salt water main and optic fibre; ·
Implementation of TTM scheme for Stage 1 pipe
laying for cooling mains and cross harbour water main at Expo Drive near
HKCEC (Area B1-1, B1-2 & B4-1); ·
Tree transplantation at Wan Chai and Tsim Sha
Tsui (to be completed by early Dec 10); ·
Builder’s work and structural modification for
Sea water pump houses / Transformer room of HKCEC (to be completed by late
Feb 11). The liaison and coordination of interfaces are ongoing; ·
Preparation work for E&M first fixing at high
level of Pump Station Nos. 1, 3, 4 & 5 (Schedule to be completed by late
Mar 2011); and
·
|
·
To conform
the installation and setting as in the silt screen deployment plan ·
Frequency
spray water on the dry dusty road and on the surface of concrete breaking ·
To cover
the dusty material or stockpile by impervious sheet ·
To space out noisy equipment and position as far
as possible from sensitive receiver. ·
To well maintain the mechanical equipments /
machineries to avoid abnormal noise nuisance. ·
Machines and plant that may be in intermittent
use should be shut down between work periods or should be throttled down to a
minimum ·
Daily
visual inspection of silt screen and silt curtain to ensure its operation
properly |
HK/2009/02 |
·
Site
clearance; ·
Dredging
in West temporary seawall construction in Area WCR1; ·
Rock
Filling and Reclamation in Area WCR1; ·
Casting,
delivery and installation of precast caisson seawalls, pumping stations and
seawall blocks; ·
Permanent
seawall construction; ·
Drainage
diversion of existing 1800mm dia. pipe for WCR1 reclamation; ·
Road
improvement at Junction of Fleming Road and Gloucester Road; ·
Road
modification at Expo Drive East; ·
Construction
of new public toilet and helipad terminal building at Expo Drive East; ·
Fabrication
and delivery of HDPE pipe for submarine outfall; ·
Installation
of ‘Z’ section of submarine outfall underneath the seawall; ·
Laying
of cooling water mains; ·
Pre-bored
H-piling at proposed WSD Salt Water Pumping Station; ·
Seawall
construction near Expo Drive East; ·
Tree
transplanting; ·
Establishing
public fill sorting facility at TKO; ·
Testing
with trial run of public fill sorting facility at TKO; ·
Trench
excavation for construction of Salt Water Intake Culvert at Wan Shing Street; ·
Piling
at new Wan Chai Ferry Pier; ·
Installation
of building services for public toilet; and
·
|
·
To cover
the dusty material or stockpile by impervious sheet; ·
Frequency
spray water on the dry dusty road and on the surface of concrete breaking ·
To well maintain
the mechanical equipments / machineries to avoid abnormal noise nuisance and dark
smoke emission ·
To conform
the installation and setting as in the silt screen and silt
curtain deployment plan ·
Movable noise barrier shall be deployed for
demolition works ·
Daily
visual inspection of silt screen and silt curtain to ensure its operation
properly |
HY/2009/15 |
·
Maintenance
dredging
works at TCBR4, TCBR2 and TCBR3 for mooring and anchorage rearrangement; ·
Place
rockfill on the seabed at TCBR2 and TCBR3; ·
Installation
of Buoys; ·
Demolition
of Ex-Fireboat Station; and ·
Erect the
CSHK’s Site Office |
·
To
conform the installation and setting as in the silt screen and silt
curtain deployment plan ·
Frequency
spray water on the dry dusty road and on the surface of concrete breaking ·
To
cover the dusty material or stockpile by impervious sheet ·
To space out noisy equipment and position as far
as possible from sensitive receiver. ·
Daily
visual inspection of silt screen and silt curtain to ensure its operation
properly |
10.0.1.In the coming month, the Contracts
HK/2009/01 and HK/2009/02 are anticipated to be
commenced on site are summarized in Table 10.2. The
construction programmes of individual
contracts are
provided in Appendix 10.1.
Table 10.2 Summary
of Key Construction Activities of Individual
Contract(s) to be commenced in
Coming Reporting Month
|
|
|
|
|
|
|
|
|